VolkerWessels UK Ltd

08/03/2026 | Press release | Archived content

VolkerGround Engineering at Rother Tidal Walls East

Working along 50 linear metres of river embankment, our team installed 12m-long AZ26-700 sheet piles using conventional piling methods across four piling gate setups.

Works commenced in May 2026, using an LR1500 lattice crawler crane and a suspended 60HV vibratory hammer to install the piles to refusal. The piles were then impact driven to final level using a CX60 hammer.

Alternative installation methods were considered during the planning phase. However, the distance between the pile line and the proposed piling platform made long-reach solutions impractical. Our chosen methodology enabled the works to be delivered safely and efficiently while minimising disruption to members of the public and road users using Monk Bretton Bridge.

Throughout the project, our team worked closely with our client, VolkerStevin, ensuring a collaborative approach that contributed to the safe and successful delivery of the works.

A great effort from everyone involved in successfully delivering this section of the project.

For further information, or to discuss your sheet piling requirements, contact [email protected]

VolkerWessels UK Ltd published this content on August 03, 2026, and is solely responsible for the information contained herein. Distributed via Public Technologies (PUBT), unedited and unaltered, on August 17, 2026 at 12:42 UTC. If you believe the information included in the content is inaccurate or outdated and requires editing or removal, please contact us at [email protected]