Traffic Impacts Related to The I-285/I-20 West Interchange Project
|
|
This project will reconstruct and widen several interstate system-to-system ramps at the I-285/I-20 West Interchange and add a combination of collector-distributor (CD) lanes or connecting lanes and auxiliary lanes along I-20 west and I-285 north of the interchange.
What: Weather permitting, the Georgia Department of Transportation (Georgia DOT) contractors will temporarily close traffic lanes at the areas identified below to perform roadwork activities on the I-285/I-20 West Interchange project.
|
|
|
Roadway
|
Activity
|
Start Date
|
End Date
|
Times
|
|
I-285 Northbound
|
|
Cascade Road to Bolton Road
|
Alternating, single, left-lane, and left-shoulder closure, and single, right-lane, and right-shoulder closure
|
Monday, October 12
|
Monday, October 19
|
9 p.m. - 5 a.m. Nightly
|
|
Cascade Road to Bolton Road
|
Alternating, double, left-lane, and left-shoulder closure, and double, right-lane, and right-shoulder closure
|
Monday, October 12
|
Monday, October 19
|
11 p.m. - 5 a.m.
Nightly
|
|
I-285 Southbound
|
|
US 78/Donald Lee Hollowell Pkwy to SR 139/MLK Jr. Drive
|
Alternating, single, left-lane, and left-shoulder closure, and single, right-lane, and right-shoulder closure
|
Monday, October 12
|
Monday, October 19
|
9 p.m. - 5 a.m.
Nightly
|
|
US 78/Donald Lee Hollowell Pkwy to SR 139/MLK Jr. Drive
|
Alternating, double, left-lane, and left-shoulder closure, and double, right-lane, and right-shoulder closure
|
Monday, October 12
|
Monday, October 19
|
11 p.m. - 5 a.m.
Nightly
|
|
SR 280/South Cobb Drive to the I-20 Interchange
|
Pacing operation, all lanes and shoulders
|
Monday, October 12
|
Thursday, October 15
|
10:30 a.m. - 12 p.m. Daily
|
|
I-20 Westbound
|
|
SR 139/MLK Jr. Drive to the I-285 Interchange
|
Pacing operation, all lanes and shoulders
|
Monday, October 12
|
Thursday, October 15
|
10:30 a.m. - 12 p.m. Daily
|
|
Anderson Avenue underpass to Riverside Parkway
|
Alternating, single, left-lane, and left-shoulder closure, and single, right-lane, and right-shoulder closure
|
Monday, October 12
|
Monday, October 19
|
9 p.m. - 5 a.m. Nightly
|
|
Anderson Avenue underpass to Riverside Parkway
|
Alternating, double, left-lane, and left-shoulder closure, and double, right-lane, and right-shoulder closure
|
Monday, October 12
|
Monday, October 19
|
11 p.m. - 5 a.m. Nightly
|
|
I-20 Eastbound
|
|
Riverside Parkway to the I-285 Interchange
|
Alternating, single, left-lane, and left-shoulder closure, and single, right-lane, and right-shoulder closure
|
Monday, October 12
|
Monday, October 19
|
9 p.m. - 5 a.m.
Nightly
|
|
Riverside Parkway to the I-285 Interchange
|
Alternating, double, left-lane, and left-shoulder closure, and double, right-lane, and right-shoulder closure
|
Monday, October 12
|
Monday, October 19
|
11 p.m. - 5 a.m.
Nightly
|
|
Other Locations
|
|
SR 70/Fulton Industrial Boulevard SB from Wendell Drive to Shirley Drive
|
Single, right-lane, and right-shoulder closure
|
Monday, October 12
|
Saturday, October 17
|
8 p.m. - 5 a.m.
Nightly
|
|
SR 139/MLK Jr. Drive NB from Old Gordon Road to Adamsville Drive
|
Single, right-lane, and right-shoulder closure
|
Monday, October 12
|
Saturday, October 17
|
8 p.m. - 5 a.m.
Nightly
|
|
DETOURS
|
|
I-20 Eastbound to I-285 Northbound ramp closure
|
Overnight closure and detour (Map)
Motorists traveling on I-20 eastbound will exit to I-285 southbound (Exit 51A), continue straight onto SR 139/Martin Luther King Jr. Drive (Exit 9), turn left onto SR 139/Martin Luther King Jr. Drive, and then turn right onto the loop ramp to I-285 northbound.
|
Monday,
October 12
|
Friday, October 16
|
9 p.m. until 5 a.m.
Nightly
|
|
I-285 Southbound to I-20 Eastbound ramp closure
|
Overnight closure and detour (Map)
Motorists traveling on I-285 southbound will continue through the interchange and exit to SR 139/Martin Luther King Jr. Drive (Exit 9), turn left onto SR 139/MLK Jr. Drive, then turn right onto the loop ramp to enter I-285 northbound and then exit right onto I-20 eastbound (Exit 10A).
|
Monday, October 19
|
Saturday, October 24
|
9 p.m. until 5 a.m.
Nightly
|
Georgia Power will conduct intermittent traffic pacing on October 10 from 7 a.m. to 4 p.m. at following locations:
-
I-20 Eastbound: From Thorton Rd (Exit 44) to I-285
-
I-20 Westbound: From Joseph E Lowry Blvd (Exit 55) to I-285
-
I-285 Northbound: From SR 154 (Exit 5) to I-20
-
I-285 Southbound: From Atlanta Rd (Exit 16) to I-20
This is to string new power lines across the interstate. If postponed due to inclement weather, the work will take place either on October 11 or the upcoming weekend (October 17,18) from 7 a.m. to 4 p.m. Drivers should expect delays and plan alternative routes.
Looking for more information about the adjacent I-285 Westside Rebuild projects?
Click here to visit the project website, learn more about the project, and view upcoming closures: https://i285w-pavement-reconst-gdot.hub.arcgis.com/
|
|
|