Overnight closures are scheduled July 23-26 near US 75 and Renner Road as crews continue bridge enhancement work for DART's Silver Line commuter rail route.
The work will take place at the Silver Line bridge over US 75, located just south of the President George Bush Turnpike. This phase is similar to the south arch installation completed in June and will include prepositioning and lifting additional arch segments into place.
Closures will vary by night and are expected to impact US 75 main lanes, frontage roads, ramps, Renner Road and President George Bush Turnpike direct connect ramps at different times. Drivers should plan ahead, allow extra travel time, follow posted detours and use alternate routes when possible.
Scheduled Traffic Impacts
Thursday, July 23 | 9 p.m.-4 a.m.
Crews are scheduled to preposition the center and east arch segments. No crane lifting is scheduled. Traffic impacts will include a full closure of the southbound US 75 frontage road, followed by temporary rolling closures through the US 75/Renner Road intersection and along the northbound US 75 frontage road.
Friday, July 24 | 9 p.m.-6 a.m.
Crews are scheduled to lift and set the center arch segment. Traffic impacts will include full closures of the southbound and northbound US 75 main lanes and full closures of the eastbound and westbound President George Bush Turnpike direct connect ramps to southbound US 75.
Saturday, July 25 | 9 p.m.-8 a.m.
Crews are scheduled to lift and set the east arch segment. Traffic impacts will include a full closure of the northbound US 75 main lanes; a left-lane closure on the northbound US 75 frontage road; and a full closure of northbound US 75 Exit 28B to the President George Bush Turnpike eastbound and westbound direct connect ramps.
Sunday, July 26 | 8 p.m.-5 a.m.
Crews are scheduled to lift and set the west arch segment. Traffic impacts will include a full closure of the southbound US 75 frontage road and Exit 27 to Renner Road.
Closure schedules are subject to change due to weather or construction conditions.