05/12/2026 | Press release | Distributed by Public on 05/12/2026 07:35
Benton County - Contractor crews are set to CLOSE the Benton County Route E bridge over Barker Creek south of Windsor for up to 60 days beginning the week of May 18 to replace the bridge, the Missouri Department of Transportation said.
Crews will demolish the existing bridge and replace it with a new structure. In addition, the contractor will guardrail the entire length of the project and new permanent striping.
The bridge also will be widened by four (4) feet to a total of 24 feet to accommodate two 10-foot-wide lanes with two-foot shoulders.
This bridge was built in 1947 and is in a deteriorating condition. Approximately 1,140 vehicles cross the bridge daily.
Traffic Impacts:
Weather and/or construction delays could alter the work schedule.
This work is part of a three-year project to improve 20 bridges in seven (7) counties in west central Missouri. Of the 20 bridges in the project, known as the Kaysinger Basin Bridge Bundle, fourteen (14) bridges will be replaced and six (6) bridges will receive major rehabilitation work. On average, these bridges have been in place for 70 years.
More information about this project can be found on the project website - Kaysinger Basin Bridge Bundle.
Project Details:
The ESS Team is a partnership of engineering and construction firms that will design and construct the project with oversight by MoDOT and the Federal Highway Administration.
For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest
Follow MoDOT's Southwest District: Facebook | X | Instagram | YouTube
Take the Challenge! Buckle Up/Phone Down