February 2 - 6 schedule:

At 57th and Halsey: Concrete forming of sidewalks, installing pedestrian pole bases

At 47th and Halsey: Sawcutting for demolision and pipe installation, storm pipe installation

February 9 - 13 schedule:

At 57th and Halsey: Pour sidewalks and corners

At 47th and Halsey: Install storm pipe, demolition of curb and sidewalks, install signal poles and wiring

Businesses Remain Open During Construction!

Even as work continues around NE 60th and Halsey Street, your local businesses are still open and ready to welcome you. Check them out!

City of Portland, OR published this content on January 29, 2026, and is solely responsible for the information contained herein. Distributed via Public Technologies (PUBT), unedited and unaltered, on January 30, 2026 at 00:15 UTC. If you believe the information included in the content is inaccurate or outdated and requires editing or removal, please contact us at [email protected]