Harbour Energy – Dvalin North – completion and start-up

The audit was conducted on 8 and 9 June 2026.

Objective

The objective was to conduct an audit of Harbour Energy and the Dvalin Nord project, with a focus on the project's completion and transition to operational status. We paid particular attention to:

  • Project management and project control
  • Experiences and lessons learned, particularly from the launch of Dvalin in 2023
  • Non-conformity handling and changes since the PDO
  • The transition from project to operation, with a particular focus on the change from Wintershall Dea to Harbour Energy, as well as a subsequent, recently completed, internal reorganisation
  • Completion and testing
  • Barrier management

Result

We identified one non-conformity related to deficiencies in the handling of non-conformities. In addition, an improvement point was identified concerning necessary resources.

What happens now?

We have asked Harbour Energy to report to us by 28 August 2026 on how the non-conformity will be addressed, and to give us their assessment of the improvement point observed.

Norwegian Ocean Industry Authority published this content on August 12, 2026, and is solely responsible for the information contained herein. Distributed via Public Technologies (PUBT), unedited and unaltered, on August 12, 2026 at 08:43 UTC. If you believe the information included in the content is inaccurate or outdated and requires editing or removal, please contact us at [email protected]