Traffic Impacts Related to The I-285/I-20 West Interchange Project
|
|
This project will reconstruct and widen several interstate, system-to-system ramps at the I-285/I-20 West Interchange and add a combination of collector-distributor (CD) lanes or connecting lanes and auxiliary lanes along I-20 west and I-285 north of the interchange.
What: Weather permitting, the Georgia Department of Transportation (Georgia DOT) contractors will temporarily close traffic lanes at the areas identified below to perform roadwork activities on the I-285/I-20 West Interchange project.
|
|
Lane Closure(s)
|
Roadway
|
Activity
|
Start Date
|
End Date
|
Times
|
|
I-285 Northbound
|
|
Cascade Road to Bolton Road
|
Alternating, single, left-lane, and left-shoulder closure, and single, right-lane, and right-shoulder closure
|
Monday, September 28
|
Monday, October 5
|
9 p.m. - 5 a.m. Nightly
|
|
Cascade Road to Bolton Road
|
Alternating, double, left-lane, and left-shoulder closure, and double, right-lane, and right-shoulder closure
|
Monday, September 28
|
Monday, October 5
|
11 p.m. - 5 a.m.
Nightly
|
|
I-285 Southbound
|
|
US 78/Donald Lee Hollowell Pkwy to SR 139/MLK Jr. Drive
|
Alternating, single, left-lane, and left-shoulder closure, and single, right-lane, and right-shoulder closure
|
Monday, September 28
|
Monday, October 5
|
9 p.m. - 5 a.m.
Nightly
|
|
US 78/Donald Lee Hollowell Pkwy to SR 139/MLK Jr. Drive
|
Alternating, double, left-lane, and left-shoulder closure, and double, right-lane, and right-shoulder closure
|
Monday, September 28
|
Monday, October 5
|
11 p.m. - 5 a.m.
Nightly
|
|
SR 280/South Cobb Drive to the I-20 Interchange
|
Pacing operation, all lanes and shoulders
|
Monday, September 28
|
Thursday, October 1
|
10:30 a.m. - 12 p.m. Daily
|
|
I-20 Westbound
|
|
SR 139/MLK Jr. Drive to the I-285 Interchange
|
Pacing operation, all lanes and shoulders
|
Monday, September 28
|
Thursday, October 1
|
10:30 a.m. - 12 p.m. Daily
|
|
Anderson Avenue underpass to Riverside Parkway
|
Alternating, single, left-lane, and left-shoulder closure, and single, right-lane, and right-shoulder closure
|
Monday, September 28
|
Monday, October 5
|
9 p.m. - 5 a.m. Nightly
|
|
Anderson Avenue underpass to Riverside Parkway
|
Alternating, double, left-lane, and left-shoulder closure, and double, right-lane, and right-shoulder closure
|
Monday, September 28
|
Monday, October 5
|
11 p.m. - 5 a.m. Nightly
|
|
I-20 Eastbound
|
|
Riverside Parkway to the I-285 Interchange
|
Alternating, single, left-lane, and left-shoulder closure, and single, right-lane, and right-shoulder closure
|
Monday, September 28
|
Monday, October 5
|
9 p.m. - 5 a.m.
Nightly
|
|
Riverside Parkway to the I-285 Interchange
|
Alternating, double, left-lane, and left-shoulder closure, and double, right-lane, and right-shoulder closure
|
Monday, September 28
|
Monday, October 5
|
11 p.m. - 5 a.m.
Nightly
|
|
Other Locations
|
|
SR 70/Fulton Industrial Boulevard SB from Wendell Drive to Shirley Drive
|
Single, right-lane, and right-shoulder closure
|
Monday, September 28
|
Saturday, October 3
|
8 p.m. - 5 a.m.
Nightly
|
|
SR 139/MLK Jr. Drive NB from Old Gordon Road to Adamsville Drive
|
Single, right-lane, and right-shoulder closure
|
Monday, September 28
|
Saturday, October 3
|
8 p.m. - 5 a.m.
Nightly
|
|
DETOURS
|
|
I-20 Westbound to I-285 Northbound ramp closure
|
Overnight closure and detour (Map)
Motorists traveling on I-20 westbound will continue through the interchange and exit to SR 70/Fulton Industrial Blvd (Exit 49), turn left onto SR 70/Fulton Industrial Blvd, then turn left onto the I-20 eastbound ramp, and then exit right onto I-285 northbound (Exit 51B).
|
Wednesday, October 7
|
Friday, October 9
|
9 p.m. until 5 a.m.
Nightly
|
|
I-20 Eastbound to I-285 Northbound ramp closure
|
Overnight closure and detour (Map)
Motorists traveling on I-20 eastbound will exit to I-285 southbound (Exit 51A), continue straight onto SR 139/Martin Luther King Jr. Drive (Exit 9), turn left onto SR 139/Martin Luther King Jr. Drive, and then turn right onto the loop ramp to I-285 northbound.
|
Monday, October 12
|
Friday, October 17
|
9 p.m. until 5 a.m.
Nightly
|
Georgia Power will have intermittent traffic pacing on I-20 and I-285, near the interchange on October 10 and October 11 from 7 a.m. to 4 p.m.
Looking for more information about the adjacent I-285 Westside Rebuild projects?
Click here to visit the project website, learn more about the project, and view upcoming closures: https://i285w-pavement-reconst-gdot.hub.arcgis.com/
|
|
|