NRC opens comments on draft EA for Crownpoint ISR project

Through December 21, the Nuclear Regulatory Commission is accepting public comments on a draft environmental assessment (EA), a draft programmatic agreement (PA), and a finding of no significant impact (FONSI) for an in situ recovery (ISR) uranium mining project covering four locations in McKinley County, N.M.

NuFuels, a subsidiary of Laramide Resources, has applied for a renewal of license SUA-1580 to construct and operate the Crownpoint Uranium Project (CUP), also known as the Crownpoint-Church Rock Uranium Project. Permitting processes for the project are being expedited under the federal FAST-41 program, with final reviews expected to be completed in May 2027. If approved, the renewed license would cover construction and operation of the project for 20 years.

Although the NRC issued the project's initial license in 1998, facility construction never began. The project has faced opposition since the license approval; most recently, in July of this year, the New Mexico Department of Justice filed a petition to intervene in the CUP license renewal process with the NRC, noting that the project sites extend into Navajo Nation land and calling for assurances that the project will meet the state's standards for groundwater protection. That petition is still being adjudicated as of this writing.

History of the CUP: The license for the CUP was initially held by another company, Hydro Resources, which filed its application with the NRC in 1988. The NRC issued the construction and operation license for the CUP a decade later, after which, according to NRC documentation, the project stalled because of ongoing litigation, fluctuations in the market for uranium, and negotiations regarding the facility between Hydro Resources and the Navajo Nation.

Hydro Resources submitted its first license renewal request for the project in 2002; however, delays persisted for similar reasons. The CUP license was transferred to NuFuels in 2018, and in 2024, the NRC requested a revised license renewal application from the current license holder.

Recent regulatory actions: NuFuels submitted the revised renewal application for the CUP in January 2025. Along with providing an updated environmental report, it also incorporated parts of the previous licensing history into its application as allowed by 10 CFR Part 51. The NRC published its notice of the application on May 27, 2026.

Two months later, the NMDOJ filed its petition to intervene, listing 10 environmental contentions and three safety contentions. Among its environmental contentions, the state claimed that NuFuels' environmental report failed to demonstrate the feasibility of restoring the Westwater Canyon aquifer below the project areas, relied on outdated hydrogeological models, and lacked any references to the Navajo Nation's legal prohibitions. In its safety contentions, the state claimed that NuFuels' mine design and characterization, assessments of existing boreholes, and financial guarantees were inadequate.

NuFuels and the NRC both submitted their responses to New Mexico's petition on August 21. While NuFuels argued that none of the state's contentions were admissible, the NRC stated that it found six of the environmental contentions and two of the safety contentions admissible and recommended that the Atomic Safety and Licensing Board grant the petition in part.

A panel from the board held a hearing with representatives from NuFuels and the NMDOJ as well as NRC staff on October 5. During the session, it was noted that the NRC had amended its position on one of the safety contentions and no longer considered the claim regarding NuFuels' financial guarantees admissible.

This was not the only change potentially made regarding the contentions in New Mexico's petition. At the end of the hearing, panel chair Michael Gibson confirmed that the November publication of the draft EA would give the NMDOJ 30 days to submit new and amended contentions. The state has yet to file such contentions as of this writing.

A ban and a moratorium: NuFuels' license renewal application comes as New Mexico and the Navajo Nation continue to deal with the legacy of uranium mining in the Southwest, going back to the first such activity on Navajo land in 1944.

In August of this year, New Mexico land commissioner Stephanie Garcia Richard issued a ban on new uranium mining projects and related activities on state lands, calling on the State Land Office to direct its attention instead to cleaning up and restoring the state's legacy uranium mine sites, which total more than 1,000.

More recently, at the 2026 ANS Winter Conference & Expo, the panel "Uranium Mine Remediation: Past, Present, and Future" examined the history of uranium mining on Navajo land in New Mexico and Arizona, which saw approximately 30 million tons of uranium ore extracted between 1944 and 1986. As a result of this activity, Navajo land now contains 523 abandoned uranium mines, where uranium waste rock sits on the surface; 230 of these sites have not been provided funding for cleanup.

The Diné Natural Resources Protection Act, which the Navajo Nation Council passed in 2005, stands as a response to this history. The act established a moratorium that prohibits uranium mining and milling on Navajo land-including land where NuFuels seeks to establish the CUP.

ANS - American Nuclear Society published this content on November 23, 2026, and is solely responsible for the information contained herein. Distributed via Public Technologies (PUBT), unedited and unaltered, on November 23, 2026 at 19:39 UTC. If you believe the information included in the content is inaccurate or outdated and requires editing or removal, please contact us at [email protected]