Roadway Activity Report for the Lower East and Upper Cumberland (April 09-15, 2026)

BRADLEY COUNTY SR-2 (N. LEE HWY.) Utility Work both directions from LM 8.12 to LM 8.14: Flagging-assisted lane closures on SR-02 (South Lee HWY) between Victory St. SW and Old Boyd Farm RD. SW Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 04/02/2026 through 04/08/2026 from 9 am - 2 pm [2025-930]

BRADLEY COUNTY SR-60 widening from the 4-lane north of I-75 (LM 17.2) to SR-306 (LM19.9): During this reporting period, the contractor will perform punch list work on SR-60 in Bradley County. Intermittent lane closures may be necessary while work occurs.
[Summers-Taylor, Inc./Cleveland/CNV130]

BRADLEY COUNTY SR-74 (SPRING PLACE RD.) Utility Work both directions from LM 11.07 to LM 11.14: Flagging-assisted lane closures on SR-74 (Spring Place Rd) between Clayton LN and Durkee RD SE. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 12/18/25 through 06/18/2026 from 9 am - 2 pm [2025-736]

BRADLEY COUNTY SR-74 [11.445-11.83] from Whaley Road to SR-60 APD-40 drainage improvements: During this reporting period, the contractor will continue storm drain installation and grading work on SR-74. Intermittent flagging operations and shoulder closures will be necessary periodically. Motorists should use caution and reduce speed when traveling through the work zone.
[APAC - Atlantic, Inc./Cleveland/CNZ243]

COFFEE COUNTY I-24 (MM 117) construction of an overpass carrying Wattendorf Memorial Highway/AEDC Road, including grading, drainage, retaining walls, and paving: On Thursday 4/8 from 9 PM to 5 AM, I-24 will be reduced to one lane and diverted to the ramps across Wattendorf Highway then back onto the interstate at exit 117. Otherwise, drivers can expect short-term flagging operations for trucks entering and exiting the work zone on Wattendorf Highway. Please use caution when traveling through the work zone. [Jones Bros. Contractors, LLC/Tullahoma/CNZ029]

COFFEE COUNTY I-24 TDOT Bridge Maintenance westbound at MM 100.2: Bridge repair operations will be completed on 04/15/2026 from 8 PM to 3 AM (pending weather). Traffic control will be in place, and THP will be assisting.

COFFEE COUNTY I-24 TDOT Contractor both directions from MM 111.2 to MM 110.8: On Thursday and Friday of this reporting period, the contractor will be closing the outside and inside shoulders on I-24 Eastbound and Westbound. This will be done during the day with no lane closures in the traffic lanes.

COFFEE COUNTY SR-55 construction from First Avenue (LM 2.0) to SR-16 (US-41A, N. Jackson St, LM 2.6) in Tullahoma: Phase 2 of roadway widening and bridge replacement on SR-55 (Wilson Ave.) will continue this week. Lanes will be reduced from 3 lanes to 2, with one lane in each direction throughout the project length. Drivers can expect intermittent flagging operations for construction operations and vehicles entering and exiting the work zone.
[Dement Construction Company, LLC/Tullahoma/CNX912]

CUMBERLAND COUNTY I-40 [304.4-306.6] from MM 304.4 to MM 306.6 bridge repair and resurfacing: The contractor has started nighttime paving activities on I-40. Temporary lane closures will be utilized throughout the project limits for the proposed work on the outside shoulders. Typical work times are Sunday night through Friday morning from 7 PM to 6 AM. Motorists should use caution in the area. [Rogers Group, Inc./Crossville/CNZ290]

CUMBERLAND COUNTY SR-101 (LANTANA RD.) Utility Work both directions from LM 1.80 to LM 2.86: Flagger-assisted lane closures on SR-101 (Lantana Rd.) between David Crockett Rd and Circle Rd. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present 04/02/2026 through 04/08/2026 from 9 am to 2 pm [2026-130)

CUMBERLAND COUNTY SR-24 [0-0.16] from Putnam County Line to C189 bridge repair: The contractor has started working on the bridge repair on I-40 at MM 304.6 or SR-24 at LM 0.24. The contractor is working behind the guardrail. Once additional work begins, additional lane closures may be necessary. Motorists should use caution in the area.
[Rogers Group, Inc./Crossville/CNZ290]

CUMBERLAND COUNTY SR-24 [15.056-15.56] from Crossville city limits to Seventh-Day Adventist Church and School bridge replacement: The contractor has closed SR-24 at LM 15.06 to LM 15.6. This closure will remain in place for the duration of the project. The posted detour is along SR-462 and SR-1. The contractor will be working on general clearing activities and utility work initially. Once initial work is completed, the contractor will proceed with the replacement of the bridge over the Obed River. Motorists should use caution and utilize the posted detour. RESTRICTIONS: Both lanes of SR-24 are closed at LM 15.06 to LM 15.6.
[Mid-State Construction Company, Inc./Crossville/CNZ206]

CUMBERLAND COUNTY SR-28 (US-127) bridge construction and paving from north of I-40 (LM 17.8) to near Potato Farm Road (LM 22.7): The contractor continues grading activities throughout the project limits. Temporary lane closures and/or periodic traffic stoppages will be necessary for construction activities. Flaggers and advanced warning signs will accompany any closures. Motorists should use caution when traveling through the work zone as traffic patterns change.
[Jones Bros. Contractors, LLC/Crossville/CNV009]

CUMBERLAND AND FENTRESS COUNTY SR-28 (US-127) widening from near N. Lowe Rd (LM 29.2) to north of SR-62 (LM 1.9): The contractor has shifted traffic to phase 2 on the newly constructed portions of SR-28 LM 0.90 to 1.98 in Fentress County. Work will proceed on the existing alignment of SR-28. Flaggers are being used intermittently as needed to control traffic through the work zone. Motorists are encouraged to use caution, be aware of new traffic signs and pavement markings, and watch for construction equipment and personnel throughout the project.
[Jones Bros. Contractors, LLC/Cookeville/CNV300]

DEKALB COUNTY SR-146 (SHORT MOUNTAIN RD.) Utility Work both directions from LM 3.55 to LM 4.38: Flagger-assisted lane closures on SR-146 (Short Mountain HWY) between Big Hickory CT and Cecil Hale Rd. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 03/02/2026 through 04/02/2026 from 9 am - 2 pm [2026-047]

DEKALB COUNTY SR-26 (US-70) grading, drainage, and construction of retaining walls and paving from near SR-53 (LM 2) to near SR-96 (LM 6.1): The contractor will continue normal working activities throughout the project limits. During this work, temporary lane closures are possible, and flaggers will be present. Motorists are encouraged to use caution while traveling through the work zone and should be aware of construction equipment adjacent to the roadway.
[Twin K Construction/Cookeville/CNV012]

DEKALB COUNTY SR-26 [15.9-20.3] from Near Old Snow Hill Road to West of Curtis Road resurfacing: The contractor is scheduled to begin concrete curb work within the project limits starting 04/15/26. During this work, the contractor will have daily lane closures set up to facilitate the work. Motorists should use caution through the work zone, and they should be prepared to stop or slow down as slow-moving traffic is encountered. [Rogers Group, Inc./Cookeville/262008]

FENTRESS COUNTY SR-28 (N. YORK HWY.) TDOT Bridge Inspection both directions at LM 29.4: A routine inspection of the SR028 truss bridge over the Wolf River will require lane closures in both directions on Monday, April 14th. Flaggers will be present to direct motorists through the work zone. Work will begin in the northbound lane at 8:30 AM and will move to the southbound lane as the inspection progresses into the afternoon. Motorists are advised to be alert to the presence of flaggers, bridge inspection personnel, vehicles, and equipment and be prepared to stop as the approach the bridge from either direction. The inspection will be completed, and normal traffic will be restored no later than 3:00 PM.

FENTRESS COUNTY SR-52 (RUGBY PK.) TDOT Bridge Inspection westbound at LM 27.83: A routine inspection of the SR-52 bridge over Clear Creek will require closure of the westbound lane and shoulder to allow inspectors to use an under-bridge access vehicle. Flaggers will be present during the inspection to direct motorists through the work zone. This inspection will begin at 8:30 AM and will be completed by 11:00 AM.

FENTRESS COUNTY SR-85 (WILDER RD.) TDOT Bridge Inspection westbound at LM 5.67: A routine inspection of the SR-85 bridge over East Fork Obey River will require closure of the westbound lane from 12 PM until 3:30 PM on Tuesday, April 14th. Flaggers will be present to direct motorists through the work zone. Motorists are advised to approach the bridge with caution. Be prepared to stop when approaching the bridge from either direction. Be alert to the presence of flaggers, bridge inspection personnel, vehicles, and equipment on the bridge during the inspection.

HAMILTON COUNTY I-75 at I-24 Interchange Reconstruction Phase 2: There is no lane closures scheduled during this time period (April 9 to April 15) for I-24 East and I-24 West from Germantown Road through the I-75 Interchange. Also, no lane closures are scheduled for I-75 North and I-75 South from Exit 1 (East Ridge) through Exit 3 (East Brainerd Road). However, it may be necessary to do short-duration (15 to 30 minutes) rolling roadblocks during the day or night for patching potholes, clearing debris or repairing guardrails, attenuators, etc.
[Wright Brothers Construction Company, Inc./Maj Prj - Blevins/DB2101]

HAMILTON COUNTY I-75 at the Hamilton Place Mall interchange: The SR-153 southbound ramp to I-75 northbound has been reduced to one lane. Traffic shifts have been implemented on I-75 northbound and I-75 southbound, Shallowford Road entrance ramps, and Shallowford Road exit ramps and the Hamilton Place Mall exit ramp. Hamilton Loop Road is closed for retaining wall construction and storm drainage installation between the intersections near Markman's Jewelers and Texas Roadhouse. The speed limit has been reduced on I-75 throughout the project limits. Nightly lane closures are permitted 8 PM to 6 AM. Motorists should use caution, paying attention to construction signage and watching for construction vehicles and personnel.
[Summers-Taylor, Inc./Chattanooga West/CNX358]

HAMILTON COUNTY SR-2 (BRAINERD RD.) Utility Work both directions at LM 14.82: Flagger-assisted lane closures on SR-2 (Brainard Rd.) between Greenway View Dr. and Old Mission Rd. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 04/02/2026 through 04/15/2026 from 9 am - 2 pm [2025-870]

HAMILTON COUNTY SR-2 (BRAINERD RD.) Utility Work both directions from LM 13.43 to LM 14.35: Flagger-assisted lane closures on SR-2 (Brainard Rd.) between Sequoia Dr and Pisgah Ave. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 04/02/2026 through 04/08/2026 from 9 am - 2 pm [2026-126]

HAMILTON COUNTY SR-2 (W. 20TH ST.) Utility Work both directions from LM 7.51 to LM 7.70: Flagger-assisted lane closures on SR-02 (West 20th St.) from Williams St. to Mitchell Ave. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present,04/09/2026 through 04/10/2026, with a rain date of 04/13/2026 from 9 am - 2 pm [2026-133]

HAMILTON COUNTY SR-319 (HIXSON PK.) Utility Work both directions at LM 8.53: Flagger-assisted lane closures on SR-319 (Hixson Pike) between Eagle Dr. and Farmstead Dr. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 02/26/2026 through 04/01/2026 from 9 pm to 5 am [2025-932)

HAMILTON COUNTY SR-321 (OOLTEWAH-RINGGOLD RD.) Utility Work both directions from LM .21 to LM .74: Flagger-assisted lane closures on SR-321 (Ooltewah Ringgold Rd.) from Mountainair Dr and East Brainard Rd. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present,04/09/2026 through 04/10/2026, with a rain date of 04/13/2026 from 9 am - 2 pm [2026-146]

HAMILTON COUNTY SR-58 (HWY. 58) Utility Work both directions at LM 19.05: Flagger-assisted lane closures on SR-58 (HWY 58) between Monger Lane and Sims Harris Rd. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 04/03/2026 from 9 am - 2 pm [2026-144]

HAMILTON COUNTY SR-58 (HWY. 58) Utility Work both directions from LM 6.69 to LM 6.83: Flagger-assisted lane closures on SR-058 (HWY 58) from Jersey Pike to Champion Rd. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 04/15/2026, with a rain date of 04/16/2026 from 9 am - 2 pm [2026-119]

HAMILTON COUNTY SR-8 (BROAD ST.) Permitted Work northbound from LM 6.21 to LM 6.23: Northbound Lane closure on SR-8 (Broad Street) between Oreo Drive and Charger Drive Motorists should reduce speed and be prepared to stop. Arrow board/message boards, flaggers, and barrels/cones will be present, 04/13/26 through 04/26/2026 from 6 am - 5 pm. [GOV-25-000062]

HAMILTON COUNTY SR-8 (SIGNAL MOUNTAIN BLVD.) TDOT Maintenance eastbound from LM 13.96 to LM 14.10: TDOT crews will be performing Roadway markings on the roadway at the intersection of Signal Mountain Boulevard and Suck Creek Road. This work will restrict traffic to 1 lane coming off the mountain. Work will begin on Tuesday, 04/21/26 at 9 am and last until 1 pm.

JACKSON COUNTY SR-53 [17.46-17.6] from south of Hurricane Branch to Near Hurricane Branch Lane culvert replacement: The contractor has completely closed the road through the work zone as of 03/04/26. Motorists need to use the posted detour route.
[Cleary Construction, Inc./Livingston/CNZ250]

MARION COUNTY I-24 TDOT Contractor eastbound from MM 157.5 to MM 161.6: Big Woody's Tree Service will be performing mechanical tree and brush removal 04/13/26 - 04/17/26 from 7 PM to 6 AM. Contractor SDM Traffic Plan will be closing lane #1 in the eastbound direction. Westbound will not be affected.

MARION COUNTY I-24 TDOT Contractor westbound from MM 156.4 to MM 141.1: MARION COUNTY I-24 TDOT Contractor, westbound from MM 156.4 to MM 141.4: Big Woody's Tree Service will be performing mechanical tree and brush removal 04/13/26 - 04/17/26 from 7 AM to 5 PM. Big Woody's will be closing the shoulder in the westbound direction. Eastbound will not be affected.

MARION COUNTY I-24 TDOT Contractor westbound from MM 156.4 to MM 164.5: MARION COUNTY I-24 TDOT Contractor westbound from MM 156.4 to MM 164.5: Big Woody's Tree Service will be performing mechanical tree and brush removal 04/06/26 - 04/10/26 from 7 AM to 5 PM. Big Woody's will be closing the shoulder in the Westbound direction. Eastbound will not be affected.

MARION COUNTY I-24 TDOT Contractor westbound from MM 157.1 to MM 158: Big Woody's Tree Service will be performing mechanical tree and brush removal 04/13/26 - 04/17/26 from 7 PM to 6 AM. Contractor SDM Traffic Plan will be closing lane #1 in the Westbound direction. Eastbound will not be affected.

MARION COUNTY I-24 [137-138.2] from 137 to 138.2 Rockfall Mitigation on I-24 near MM 137: The contractor will be performing rockfall mitigation operations on I-24 WB beginning at MM 138.2 in Marion County. The middle lane, right lane, and right shoulder have been closed. 2 Lanes of traffic have been shifted to flow on the left shoulder and left lane. Blasting will also occur during the weekdays between 9 AM and 3 PM. Blasting operations will require a rolling roadblock. All lanes will be reopened to traffic by May 22, 2026. Work will continue off the road after May 22, and the project will be completed by July 31, 2026. [Summers-Taylor, Inc./Dunlap/N262018]

MARION COUNTY SR-108 [2.8-3.24] slide mitigation: The contractor will be performing slide mitigation operations, including grading, drainage, and paving on SR-108 in Marion County at LM 2.8. The roadway will be reduced to one lane controlled by temporary traffic signals. The project completion date is 08/31/2027. Please use caution when driving through the work zone.
[Wright Brothers Construction Company, Inc./Dunlap/CNZ226]

MARION COUNTY SR-2 [17.2-17.3] from 17.2 to 17.3 construction: The contractor will be performing grading and drainage operations on SR-2 in Marion County near LM 17.25. This work will require a lane shift for the EB traffic; the WB traffic will be unaffected. Please slow down and use caution when driving through the work zone. [Talley Construction Company, Inc./Dunlap/CNZ244]

PICKETT COUNTY SR-111 (LIVINGSTON HWY.) Utility Work both directions from LM 1.46 to LM 2.52: Flagger-assisted lane closures on SR-111 (Livingston HWY) between Obey Park Rd and Cherrytree Lane. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 03/16/2026 through 04/17/2026 from 9 am - 2 pm [2026-102]

PICKETT COUNTY SR-28 (US-127) Utility Work, both directions from LM 4.72 to LM 6.07: Flagger-assisted lane closures on SR-28(North York HWY) between Koger Mountain RD and Kirk Davidson Rd. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 04/01/2026 through 04/08/2026 from 9 pm to 5 am [2026-111]

POLK COUNTY SR-68 over SR-40 the construction of bridges: During this reporting period, the contractor will continue construction on the SR-68 South bridge. All SR-68 traffic will use the newly constructed SR-68 North bridge while construction occurs on the new SR-68 South bridge. All SR-40/SR-68 interchange traffic will utilize the SR-68 North interchange ramps. A temporary 3-way stop has been implemented at the intersection of the SR-40 interchange ramp and SR-68. Motorists are encouraged to slow down when entering the construction zone and look out for new stop signs on SR-68 near the SR-40/SR-68 interchange. Traffic on SR-40 will be temporarily shifted with intermittent lane closures between the hours of 6 PM and 6 AM on 04/16/2026 and 04/17/2026. Flaggers will be present to help direct traffic. [Wright Brothers Construction Company, Inc./Cleveland/CNZ042]

PUTNAM COUNTY I-40 [303.6-304.2] from MM 303.6 to MM 304.2 bridge repair and resurfacing: The contractor has started nighttime paving activities on I-40. Temporary lane closures will be utilized throughout the project limits for the proposed work on the outside shoulders. Typical work times are Sunday night through Friday morning from 7 PM to 6 AM. Motorists should use caution in the area. [Rogers Group, Inc./Crossville/CNZ290]

PUTNAM COUNTY SR-136 construction from north of the SR-111 interchange to south of the I-40 interchange: The contractor will continue normal working activities throughout the project limits. During this work, temporary lane closures are possible, and flaggers will be present. Pigeon Roost Creek Road is closed at the intersection of SR-136, with detour signs to utilize Bunker Hill Road. Motorists are encouraged to use caution while traveling through the work zone and should be aware of construction equipment adjacent to the roadway. [Rogers Group, Inc./Cookeville/CNV284]

PUTNAM COUNTY SR-24 (CROSSVILLE HWY.) Utility Work both directions from LM 35.55 to LM 38.09: Eastbound and Westbound Lane closures on SR-24 (Crossville Hwy.) between E. Wilder Ave. and Walker Farm Rd. Motorists should reduce speed and be prepared to stop. Arrow board/message boards, flaggers, and barrels/cones will be present, 11/06/25 through 05/06/2026 from 9 am - 2 pm. [2025-521]

REGION 2 Interstate and state route thermoplastic marking re-tracing.: Contractor will be placing thermoplastic pavement markings along SR-28 (LM 14.971 - 17.810) and SR101 (LM 18.030 - 26.600) in Cumberland County, Dekalb County SR-26 (LM 6.100 - 10.880), Fentress County SR-28 (LM 10.395 - 16.400), Overton County SR-52 (LM 6.500 - 10.155) and SR-111 (LM 0.000 - 9.370), Putnam County SR-24 (LM 15.710 - 23.723) and SR-135 (LM 7.380 - 9.750), and White County SR-1 (LM 7.700 - 8.700). During this work, the contractor will be utilizing a mobile operation, and motorists should expect a delay. Motorists should exercise caution when crews are present and be aware of wet edge lines. [Mullen's Markings, Inc/Cookeville/262003]

REGION 2: The drain cleaning on various Interstate and State Routes: Drain cleaning operations are planned on I-75 and I-24 in Hamilton County. These operations are mobile along the inside shoulders with impacts to adjacent traffic lanes and will occur at night between 8 PM and 6 AM.
[Sweeping Corporation of America, Inc./Chattanooga West/CNZ286]

REGION 2 The on-call cable barrier repair on various Interstate and State Routes: The contractor will have short-term shoulder and/or lane closures in order to perform cable barrier rail repair. These closures will take place daily, Monday through Friday, during daylight hours on the interstates and some major divided highway state routes. There may also be nightly Sunday through Thursday from 7 PM to 6 AM, rarely and only as needed. At least one travel lane will remain open to traffic at all times. Typically, only a shoulder closure will be used in the median, but lane closures will be employed as needed. [LU, Inc./McMinnville/CNZ205]

REGION 2 The on-call guardrail repair and new guardrail installation on various Interstate and State Routes: The contractor will have short-term shoulder and/or lane closures to perform guardrail repair. These closures will take place on the interstate nightly Sunday through Thursday from 7 PM to 6 AM and daily Monday through Friday on state routes. At least one travel lane will remain open to traffic at all times on the interstate, and flaggers will be present on state routes during any work that is performed. [Reynolds Fence and Guardrail, Inc./McMinnville/CNZ112]

REGION 2 The random on-call attenuator repair on various Interstate and State Route: The on-call attenuator repair contractor will have a lane closure for attenuator repair in Putnam County on SR-136 LM 2.2. Work will occur during evening hours from 7 PM to 1 AM on 04/9/26 with backup date of 04/10/26 in case of inclement weather. [LU, Inc./McMinnville/CNZ118]

REGION 2 the sweeping on various Interstate and State Routes: Sweeping operations are planned throughout Region 2 this reporting period. Sweeping operations are mobile operations along the inside and outside shoulders with impacts to adjacent traffic lanes. These operations will occur at night between 8 PM and 6 AM for interstates and high traffic state routes, while daytime sweeping can be anticipated between 9 AM to 3 PM for lower traffic state routes.
[Spears-Hopkins Paving Co., LLC/Chattanooga West/CNZ248]

RHEA COUNTY SR-30 (DAYTON MTN. HWY.) Utility Work both directions at LM 3.86: Flagger assisted lane closures on SR-30 (Rhea County HWY) from Laurel Rd to Black Oak Ridge Rd. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present,04/09/2026 with a rain date of 04/13/2026 from 9 am - 2 pm [2026-152]

VANBUREN COUNTY SR-111 [14.87-19.54] from Sparta Street to White County Line microsurfacing: The contractor will have occasional lane closures during daylight hours from 6 AM to 7 PM for sign and traffic control device installations and to begin bridge repair and microsurfacing-related operations as needed. Additionally, lane closures on this multi-lane highway will occasionally carry through nighttime hours (24-hour lane closures) with proper signage for curing of concrete and other bridge-related setup. [Asphalt Paving Systems, Inc./McMinnville/CNZ177]

WHITE COUNTY SR-111 [15.25-16.25] from O'Connor Rd to Old Kentucky Rd culvert replacement: The left lane of both the Northbound and Southbound side of SR-111 will be closed until further notice. At this time the contractor will be constructing median crossovers to allow for later work to be completed. Motorists are encouraged to use caution as they approach the work zone, and they should be prepared to stop. Motorists should also be aware of the speed limit reduction in place and follow all signs displayed.
[Rogers Group, Inc./Cookeville/CNZ902]

RESTRICTIONS

CUMBERLAND COUNTY - CNZ206: Both lanes of SR-24 are closed at LM 15.06 to LM 15.6.

###

State of Tennessee published this content on April 09, 2026, and is solely responsible for the information contained herein. Distributed via Public Technologies (PUBT), unedited and unaltered, on April 09, 2026 at 19:51 UTC. If you believe the information included in the content is inaccurate or outdated and requires editing or removal, please contact us at [email protected]