Illinois Department of Transportation

05/22/2026 | Press release | Distributed by Public on 05/22/2026 15:48

Next two I-57/74 interchange ramps scheduled for four-week closures - others to follow

CHAMPAIGN - The Illinois Department of Transportation announced that the eastbound Interstate 74 to northbound Interstate 57 ramp is scheduled to close starting May 26. Additionally, the northbound I-57 to westbound I-74 ramp will close starting June 2. Both ramps are expected to be closed for four weeks.

Motorists should continue as follows:

  • Eastbound to northbound motorists should continue to take the eastbound to northbound exit to head south for detour.
  • Westbound to northbound motorists should continue to take the westbound to northbound exit to head south for detour. (northbound to Olympian Drive.)

The closures are necessary as work progresses on the final stages of the $251.8 million upgrade project. This work involves tying all new ramps and bridges into the newly constructed I-57 and I-74 lanes with permanent connections.

Similar ramp closures on the I-57/74 interchange will occur for up to four weeks each following this estimated schedule: (Closures are weather dependent and subject to change.)

  • The I-57 southbound from Olympian Drive ramp CLOSED
  • The northbound I-57 to Olympian Drive ramp, May 26-June 26.
  • The westbound I-74 to southbound I-57 ramp, July 23-Aug. 20.
  • The northbound I-57 to eastbound I-74 ramp, July 8-July 22.
  • The eastbound I-74 to southbound I-57 ramp, July 23-Aug. 20.
  • The southbound I-57 to eastbound I-74 ramp, July 23-Aug. 20.
  • The westbound I-74 to northbound I-57 ramp, May 26-June 26.
  • The southbound I-57 to westbound I-74 ramp, June 24-July 22.

The overall project is expected to be mostly completed by the end of the year, with final striping and landscaping continuing into spring 2027. For more information, visit the project website.

Motorists can expect delays and should allow extra time for trips through this area. To avoid the work area, when feasible, use of alternate routes should be considered. Drivers are urged to pay close attention to changed conditions and signs in the work zones, obey the posted speed limits, refrain from using mobile devices and be alert for workers and equipment.

Over the next six years, IDOT is planning to improve 7,107 lane miles of highway and 8.4 million square feet of bridge deck as part of Rebuild Illinois, which is investing $33.2 billion into all modes of transportation. Accomplishments through Year Six of Rebuild Illinois include almost $20.8 billion of improvements statewide to 21,309 lane miles of highway, 815 bridges and 1,181 additional safety improvements.

For more information on IDOT projects, click here. For IDOT District 5 updates, follow us on Twitter at @IDOTDistrict5 or view area construction details on IDOT's traveler information map on GettingAroundIllinois.com.

Illinois Department of Transportation published this content on May 22, 2026, and is solely responsible for the information contained herein. Distributed via Public Technologies (PUBT), unedited and unaltered, on May 22, 2026 at 21:48 UTC. If you believe the information included in the content is inaccurate or outdated and requires editing or removal, please contact us at [email protected]