Central Avenue Inlet Repairs
WINNEBAGO COUNTY, Ill. -
Central Avenue, between Montrose Avenue and Halsted Road, will be under construction starting on Thursday, October 15th with an anticipated completion date of November 15th, 2026. The work includes drainage inlets replacement/repairs and other ancillary work. Duration of the work is weather dependent. Central Avenue will remain open to traffic, but there will be intermittent lane closures and delays should be expected during this time. Please use caution in construction zones.
###