Home | In The News | Prefabricated White Space Module Time Study: Lessons from a High-Density Liquid-Cooled Deployment
Schneider Electric has published a white paper co-authored with Compass Datacenters on how prefabricated IT pods, also called white space modules, speed up high-density, liquid-cooled deployments. The study draws on installations at a Compass campus.
Schneider Electric and Compass developed the pod together for a high-density, liquid-cooled data hall. Each pod took 15 hours to install on site, compared with 75.5 hours for a traditional buildout. That's an 80% reduction. Most of the time saved comes from building and testing power distribution, cooling piping, containment and cable pathways in the factory while site preparation goes on at the same time.
Installation also got faster with repetition, dropping from 18 to 15 hours between observed deployments. Eric Williams of Compass wrote the paper with Wendy Torell and Melissa Rodriguez of Schneider Electric.
Compass Datacenters does data centers differently. The company develops and operates sustainable Class A, Community-First campuses guided by a 100-year neighbor philosophy that invests in the workforce, infrastructure, and well-being of every community it calls home. Backed by the institutional strength of Ontario Teachers' Pension Plan, Brookfield Infrastructure and KKR, Compass delivers high-quality facilities at speed for the cloud and hyperscale customers driving today's economy. By combining industrialized, prefabricated design with advanced hybrid cooling that uses no water during operations, responsible energy use, and zero-waste construction, Compass takes a more sustainable approach to digital infrastructure supporting the company's built-to-last vision. The result is move-in ready capacity that scales efficiently and responsibly. Data Centers Done Differently.
14555 N. Dallas Parkway, Suite 125
Dallas, Texas 75254