Project Update | September 12, 2025

September 12, 2025

The City appreciates your ongoing patience with the work associated with this project. Additional information regarding this project can be found at www.DurhamNC.gov/5386

Here's the schedule for the next two weeks:

Week of September 15-19 - work at Peachtree Place & Liberty Street

  • 8" waterline installation and testing
  • Traffic control at the Peachtree Place/Liberty Street intersection
  • Install 1" service line on Peachtree Place

Week of September 22-26 - work at Peachtree Place & Liberty Street

  • 8" waterline installation
  • On Tuesday, September 23, it is anticipated there will be an apartment entrance detour on Liberty Street for water tie in work. Apartment entrance will be detoured.
  • 6" and 16" waterline ties on western portion of Liberty Street
  • On Thursday, September 25 it is anticipated that crews will perform an asphalt trench repair on Liberty Street and the apartment building entrance. The apartment entrance will be detoured.

For more information, visit the project's webpage at www.DurhamNC.gov/5386

City of Durham, NC published this content on September 12, 2025, and is solely responsible for the information contained herein. Distributed via Public Technologies (PUBT), unedited and unaltered, on September 12, 2025 at 17:10 UTC. If you believe the information included in the content is inaccurate or outdated and requires editing or removal, please contact us at [email protected]