Project Update | September 19, 2025

September 19, 2025

The City appreciates your ongoing patience with the work associated with this project. Additional information regarding this project can be found at: https://www.durhamnc.gov/2780/American-Tobacco-District-Waterline-Repl .

Planned Road / Lane Closures will occur as follows:

  • Week of 9/22:
    • Southbound lane closure in Willard St between Yancey St and Blackwell St
    • Eastbound lane closure in Pettigrew St between Chapel Hill St and Blackwell St
    • Lane shifts in Chapel Hill St between Willard St and Pettigrew St
    • Detour route and construction areas for week of 9/22
  • Week of 9/29:
    • Southbound lane closure in Willard St between Yancey St and Blackwell St
    • Eastbound lane closure in Pettigrew St between Chapel Hill St and Blackwell St
    • Lane shifts in Chapel Hill St between Willard St and Pettigrew St
    • Detour route and construction areas for week of 9/22

Saturday and Sunday - September 20-21, 2025:

Week of September 22-26, 2025

  • Willard Street between Yancey Street and Blackwell Street will have a southbound lane closure to accommodate waterline installation.
    • Traffic control signs and markings will be used for the lane closure.
    • Southbound traffic will be detours via Jackson, Vickers, and Morehead.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM.
    • No water or sewer service disruptions are anticipated.
  • Pettigrew Street between Chapel Hill Street and Blackwell Street will have a eastbound lane closure to accommodate waterline installation.
    • Traffic control signs and markings will be used for the lane closure.
    • Eastbound traffic will be detoured via Ramseur and Corcoran / Blackwell streets.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM.
    • No water or sewer service disruptions are anticipated.
  • Chapel Hill Street between Willard Street and Pettigrew Street will have lane shifts to accommodate waterline installation.
    • Traffic control signs and markings will be used for the lane shift. Traffic will be maintained in both directions.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM.
    • No water or sewer service disruptions are anticipated.

Saturday and Sunday - September 27-28, 2025:

Week of September 29 - October 3, 2025

  • Willard Street between Yancey Street and Blackwell Street will have a southbound lane closure to accommodate waterline installation.
    • Traffic control signs and markings will be used for the lane closure.
    • Southbound traffic will be detours via Jackson, Vickers, and Morehead.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM.
    • No water or sewer service disruptions are anticipated.
  • Pettigrew Street between Chapel Hill Street and Blackwell Street will have a eastbound lane closure to accommodate waterline installation.
    • Traffic control signs and markings will be used for the lane closure.
    • Eastbound traffic will be detoured via Ramseur and Corcoran / Blackwell streets.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM.
    • No water or sewer service disruptions are anticipated.
  • Chapel Hill Street between Willard Street and Pettigrew Street will have lane shifts to accommodate waterline installation.
    • Traffic control signs and markings will be used for the lane shift. Traffic will be maintained in both directions.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM.
    • No water or sewer service disruptions are anticipated.

Project contacts:

Wade Tong, Construction Team Manager, City of Durham, [email protected]

CJ Rizzo, Project Manager, Teraflex Group LLC, [email protected]

City of Durham, NC published this content on September 19, 2025, and is solely responsible for the information contained herein. Distributed via Public Technologies (PUBT), unedited and unaltered, on September 19, 2025 at 12:46 UTC. If you believe the information included in the content is inaccurate or outdated and requires editing or removal, please contact us at [email protected]