04/21/2026 | Press release | Distributed by Public on 04/21/2026 15:19
The proposed Andytown-Oasis transmission lines project includes four new transmission lines:
• One 500kV line starting at FPL's existing Andytown substation in Broward County and ending at FPL's planned Oasis substation in Miami-Dade County;
• One 500kV line starting at FPL's existing Quarry substation in Miami-Dade County and ending at FPL's planned Oasis substation in Miami-Dade County;
• One 230kV line starting at FPL's planned Oasis substation in Miami-Dade County and ending at FPL's existing Quarry substation in Miami-Dade County;
• One 230kV line starting at FPL's planned Oasis substation in Miami-Dade County and ending at FPL's existing Levee substation in Miami-Dade County.
The hearing is scheduled for the following time and location:
Thursday, April 23, 2026
9:30 a.m. (EDT)
Betty Easley Conference Center
Joseph P. Cresse Hearing Room (Room 148)
4075 Esplanade Way
Tallahassee, Florida
A live broadcast of the hearing will be available on the PSC's website (click "Watch Live and Archived PSC Events") and may be broadcast on the Florida Channel (check your local listing).