Macon-Bibb County…
I-16/I-75 Interchange Improvement Project Updates: June 12, 2026, - June 19, 2026; Lane Closures Next Week
MACON-BIBB - Contractors for the Georgia Dept of Transportation (GDOT) will continue construction activities related to the I-16/I-75 Interchange Improvement Project next week in Macon-Bibb. Weather and on-site conditions permitting, the scheduled activities beginning Friday, June 12, 2026, through Friday, June 19, 2026, are listed below.
Lane Closure:
Mon. June 15 through Fri. June 19 nightly 9 p.m. until 5 a.m. the following mornings:
-
Alternating single lane closures on Spring St.
-
Alternating single lane closures on Second St.
Mon. June 15 9 p.m. until 5 a.m. the following morning:
-
Single Lane closures/Traffic Shift to the right shoulder on I-75 NB from M.P. 166 to M.P. 168
Construction Activities for June 12 - June 19, weather and on-site conditions permitting:
Phase 6: from I-75 Southbound/I-75 Northbound
-
Pole/Line Relocations along Riverside Rd.
-
Continue installing erosion control devices
-
Roadway construction on I-75 shoulders for future traffic shift
Phases 4 and 5: from I-16 westbound/I-75 to Walnut Creek
-
Continue construction of bridge superstructure for I-16 Spring Street entrance and exit ramps.
-
Continue construction of new Second Street bridge superstructure.
-
Continue construction of one new I-16 westbound bridge superstructures.
-
Continue construction of two new I-16 eastbound bridge superstructures
-
Pouring bridge deck spans and edge beams on new I-16 eastbound bridge superstructure.
-
Continue construction of two new I-16 westbound entrance ramps.
-
Continue demolition of bridge ramp to I-16 eastbound.
-
Continue construction of new MSE (retaining) walls along I-75 northbound and southbound and other walls throughout the project.
-
Installing pipe and other drainage structures throughout the project area.
Phase 2 and 3: I-75 from Hardeman Avenue to I-16 eastbound
-
Continue repair and reinstallation of sidewalks and ADA-compliant ramps.
-
Continue installation of the street lighting throughout the project on I-75.
-
Construction of concrete sound and visual walls along I-75 northbound and southbound continues.
Phase 1: I-16 from the I-16/ I-75 split to the Martin Luther King Jr. Boulevard exit.
-
Evaluating project area for remaining work items.
Advisory: Dates may change due to weather or other factors. Motorists are advised to expect delays, exercise caution, and reduce their speed while traveling through work zones. Before heading out, get real-time information on work status and traffic conditions. Call 511, visit 511ga.org, or download the Georgia 511 app.
###
The Georgia Department of Transportation plans, constructs and maintains Georgia's state and federal highways. We're involved in bridge, waterway, public transit, rail, geThe I-16/I-75 Interchange Improvement Project is a $620 million safety and mobility megaproject. With its massive scope to widen and reconstruct I-16, I-75 and their interchange in Macon-Bibb, this project is being delivered in seven design and construction phases that will continue through 2030. When complete, new CD lanes, additional interstate lanes, new interstate on-and off-ramps, upgrades to 11 bridges, new walls, upgraded drainage systems, etc. will deliver safer and improved mobility for Macon-Bibb's local commuters and businesses, regional travelers and commercial freight from the Georgia southern coast to destinations within the state and throughout the U.S.
neral aviation, bike and pedestrian programs. And we help local governments maintain their roads. Georgia DOT and its nearly 4,000 employees are committed to delivering a transportation system focused on innovation, safety, sustainability and mobility. The Department's vision is to boost Georgia's competitiveness through leadership in transportation.
|
|
|