Herring Avenue Bridge Update: Westbound Closures to Begin May 26

Herring Avenue Bridge Update: Westbound Closures to Begin May 26

Published on May 14, 2026

Construction continues on the Herring Avenue Bridge over the Brazos River. Starting Tuesday, May 26, the westbound side of the bridge from
N. Martin Luther King, Jr. Blvd. to N. University Parks Drive will be closed for about one month depending on weather and construction activities.

  • A detour will be in place directing traffic to Waco Drive and up Fourth Street to return to Herring Ave.
  • Crews will be replacing bridge joints and completing overlay work.
  • Before crews close the westbound lanes, the pedestrian walkway and the right lane on the eastbound side will be reopened to traffic.

Detour Map

How to use this map: Click the colored routes on the map for more information on each specific detour.

Route Legend

  • Red: Bridge closure
  • Dark Green: Primary detour route
  • Orange: Detour route for westbound traffic on Herring Ave.
  • Light Green: Detour route for eastbound traffic on N. M.L.K. Blvd (north of Herring Ave.)
  • Purple: Detour route for eastbound traffic on N. M.L.K Blvd (south of Herring Ave.)
  • Blue: Detour route for eastbound traffic on N. M.L.K Blvd (south of Faulkner Lane)

Eastbound Closure

Once the westbound side is completed, the closure will shift to the eastbound side.

  • A similar detour will be in place directing traffic to Fifth Street, Waco Drive, and Dallas Street to return to Herring Ave.
  • The eastbound closure is anticipated to last about two months depending on weather and construction activities.
  • Crews will be completing joint replacement, overlay, and guardrail work.

About the Project

The Herring Avenue Bridge Project includes bridge rail and pedestrian walkway improvements, bridge joint replacements, vegetation removal, minor concrete repairs, a polymer concrete overlay, and replacement of outdated or damaged guardrails. The project is anticipated to be complete in fall 2026.

Bridges require periodic maintenance and repair to mitigate degradation and extend their useful life. The City of Waco has identified repairs that are still manageable from a cost standpoint, so we are completing them now before they worsen and become more expensive.

Thank You for Your Cooperation

Please adhere to all posted signage near the bridge, which will be placed in advance to warn of upcoming work. Message boards will also be posted ahead of any half-bridge closure to notify drivers and direct traffic to established detours.

We urge all residents to drive carefully through the construction zones. We sincerely thank you for your patience and cooperation as we work to ensure the long-term safety and reliability of the Herring Avenue Bridge.

Stay Informed

For the latest information regarding construction, lane closure schedules, and detour routes, please check this page and our official social media channels.

Tagged as:
City of Waco, TX published this content on May 14, 2026, and is solely responsible for the information contained herein. Distributed via Public Technologies (PUBT), unedited and unaltered, on May 14, 2026 at 15:52 UTC. If you believe the information included in the content is inaccurate or outdated and requires editing or removal, please contact us at [email protected]