Henry County - The closure of the Henry County Route Y bridge over East Tebo Creek south of Windsor is being pushed out to the week of August 10, the Missouri Department of Transportation said.
Once the work begins, the bridge will be closed for up to 73 days for replacement.
The plan was to close the bridge next week, but that was postponed until all nearby utilities have been relocated.
Crews will demolish the existing single-lane bridge and replace it with a new structure. The new bridge will be four feet wider than the current one to accommodate two (2) lanes. In addition, the contractor will add new barrier walls on both sides of the bridge along with guardrail and new permanent pavement striping.
This bridge was built in 1934. Approximately 604 vehicles cross the bridge daily.
Traffic Impacts:
Weather and/or construction delays could alter the work schedule.
This work is part of a three-year project to improve 20 bridges in seven (7) counties in west central Missouri. Of the 20 bridges in the project, known as the Kaysinger Basin Bridge Bundle, fourteen (14) bridges will be replaced and six (6) bridges will receive major rehabilitation work. On average, these bridges have been in place for 70 years.
More information about this project can be found on the project website - Kaysinger Basin Bridge Bundle.
Project Details:
The ESS Team is a partnership of engineering and construction firms that will design and construct the project with oversight by MoDOT and the Federal Highway Administration.
For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest . To receive the latest news and text alerts, sign up for e-updates .