COLOMA, Mich. - The Michigan Department of Transportation (MDOT) and contractor Pavement Maintenance Systems Inc. are chip sealing 27 miles of state highways in four locations:
This $2.9 million investment includes overband crack fill, single-course chip seal, fog seal and pavement markings.
Counties:
Berrien and Van Buren
Highways:
I-196, I-196 BL and M-63
Closest communities:
Covert, South Haven
Start date:
Monday, June 15, 2026
Estimated end date:
Thursday, Sept. 3, 2026
Traffic restrictions:
Single-lane closures, traffic shifts and traffic regulators.
Jobs numbers:
Based on economic modeling, this investment is expected to directly and indirectly support 25 jobs.