Newcleo, a nuclear development firm based in France, has announced that it will partner with U.S.-based Curio to source material for the former's planned mixed oxide (MOX) fuel fabrication plant, which it intends to construct at the Department of Energy's Savannah River Site in South Carolina.
The agreement, announced on November 16, would see Curio use its NuCycle nuclear fuel recycling technology to recover plutonium, uranium, and other materials from used fuel. Newcleo would then use the materials to fabricate MOX fuel at its proposed facility. The two companies intend to collaborate on additional R&D activities to develop nuclear recycling technology.
Although Newcleo has not yet submitted a licensing application for the facility to the Nuclear Regulatory Commission, it submitted a preapplication regulatory engagement plan on August 3, noting that it plans to apply for a license under 10 CFR Part 70. The move came approximately five weeks after the company submitted a regulatory engagement plan to the NRC for another project: its LFR-AS-200 lead-cooled fast reactor.
According to Newcleo, the MOX fuel it fabricates at its Savannah River facility would be compatible with its LFR-AS-200 reactors as well as other advanced reactors and certain existing light water reactor designs. Newcleo also aims to construct a reactor at SRS.
Additionally, Curio states that its NuCycle technology, which would produce the feedstock for the facility, aligns with the requirements of the Nuclear REFUEL (Recycling Efficient Fuels Utilizing Expedited Licensing) Act, which is currently under deliberation in Congress.
The Nuclear REFUEL Act: Originally introduced in the House of Representatives in December 2024 and reintroduced as part of the 119th Congress in June 2025, the Nuclear REFUEL Act proposes a redefinition of nuclear fuel "production facilities" under 1954's Atomic Energy Act.
Under the new legislation, instead of being licensed as production facilities, reprocessing facilities producing uranium-transuranic mixed fuel would qualify for licensing under 10 CFR Part 70, the same regulatory framework that applies to other fuel facilities. Proponents of the Nuclear REFUEL Act say that this would streamline requirements for reprocessing and recycling facilities, including, presumably, a facility that uses Curio's NuCycle technology.
The Nuclear REFUEL Act passed in the House of Representatives on November 9 and, as of this writing, has been read twice in the Senate. Should it become law, it would facilitate production of a type of nuclear fuel that the United States has explored but not yet produced commercially.
The MFFF: While several nations, including France, Belgium, and Switzerland, have used MOX fuel in their reactors for decades, the United States has not been producing MOX fuel during this time.
However, Newcleo's proposed South Carolina facility is not the first MOX fabrication facility that has been attempted in the United States-or at Savannah River-in the 21st century. In 2005, the NRC approved a construction license for the Mixed Oxide Fuel Fabrication Facility (MFFF) at SRS.
The MFFF, which was to have been administered by the DOE's National Nuclear Security Administration, was designed as a result of a bilateral agreement between the United States and Russia-the Plutonium Management and Disposition Agreement, enacted in 2000-to reduce both countries' stocks of weapons-grade plutonium. The MFFF was to do so by processing plutonium into MOX fuel, which would render it less susceptible to proliferation efforts. The agreement between the two nations was bolstered at the April 2010 Nuclear Security Summit, at which the United States and Russia committed to disposing of 34 metric tons each of surplus weapons-grade plutonium.
However, construction delays and increasing costs led the Obama administration to issue a request to terminate work on the project for fiscal year 2017; the first Trump administration followed in fiscal year 2018 with a directive to pursue an option known as "dilute and dispose" for disposing of the surplus plutonium. On October 12, 2018, the DOE and NNSA sent the facility contractor a Notice of Termination to cease construction work on the MFFF, and on February 8, 2019, the NRC terminated the facility's construction authorization.
Yet even that was not the end of the story for the MFFF. In 2022, the DOE contracted Aecon-Wachs to assist in converting the MFFF facility into a plutonium processing plant. The Savannah River Plutonium Processing Facility will produce plutonium pits to support the NNSA's mission of nuclear deterrence; full authorization for construction of the facility was issued on October 15 of this year.
Additionally, in March 2026, the DOE announced that it would restart the HB Line facility, a separate facility at SRS that was constructed in the 1980s to produce plutonium-238 for space exploration missions but was closed in 2018. Upon readiness, HB Line will serve as a facility to produce MOX fuel for advanced reactors.