09/23/2026 | Press release | Distributed by Public on 09/23/2026 13:34
In a significant development for the rapidly expanding Texas data center market, Gov. Greg Abbott has directed the Texas Commission on Environmental Quality (TCEQ) to halt permitting for data center projects until ongoing state audits evaluating impacts on electric reliability and water resources are completed. According to the governor's Sept. 21 announcement, no state agency should move forward with regulatory approvals related to data center development until data necessary for those audits has been obtained and reviewed. The directive follows recent actions requiring audits by the Public Utility Commission of Texas (PUCT), Electric Reliability Council of Texas (ERCOT) and Texas Water Development Board (TWDB).
Abbott stated that "Texans must come first" and directed TCEQ to issue no permits sought by data center projects while ERCOT and TWDB evaluate the industry's impact on grid reliability, security, water usage and infrastructure costs. The governor also emphasized that data centers should bear their own infrastructure costs, comply with electricity and water reporting requirements and avoid adverse impacts on local communities. The administration has further indicated that it will pursue legislation to eliminate financial incentives for data centers during the next legislative session.
As Abbott indicated in his letter to TCEQ to halt permitting, "[b]ecause the information sought by the PUC, ERCOT, and TWDB is necessary to make informed decisions by each of those agencies, no other state agency shall move forward with regulatory approvals related to data centers until this information is acquired." Accordingly, the permitting halt extends to all state agency approvals required for data center developments.
Texas has emerged as one of the nation's leading data center markets due to abundant land, favorable business conditions and access to significant electric generation resources. The state's increasing scrutiny of large-load facilities reflects growing concerns regarding:
The governor's directive creates uncertainty for projects currently in development and may result in delays for permitting, financing, site selection, interconnection planning, construction schedules and related transactions.
The directive extends beyond traditional data center developers. Potentially affected stakeholders include:
Companies pursuing Texas projects should closely monitor evolving requirements from ERCOT, PUCT, TWDB and TCEQ, as well as anticipated legislative proposals that could alter siting, permitting, water-use, reporting, incentive and infrastructure cost-recovery frameworks.
BakerHostetler's national Data Center Project Development team regularly advises clients on complex data center development matters, including permitting and environmental compliance, ERCOT and utility regulatory issues, power supply arrangements, transmission and interconnection matters, water-use considerations, tax incentives, real estate acquisition and development, project financing, government affairs and litigation risk. Our multidisciplinary team is actively tracking Texas regulatory and legislative developments and can help clients assess project impacts, manage permitting risks, engage with regulators and position projects for successful development in an increasingly complex regulatory environment.