09/19/2025 | Press release | Distributed by Public on 09/19/2025 11:52
The City of Menifee has street project and construction updates to share with the community: *COMPLETE* Haun Road - Paving and Striping
Striping and paving working has been completed on Haun Road. All lanes are now open.
Bradley Road at Rio Vista Drive and Potomac Drives - Bradley Road Bridge Project
Pile drilling activities have been successfully completed. The contractor is currently in the process of constructing the abutment footing and will start work on the column foundation.
Ethanac Road - Pulte Homes Development Project
Pulte Homes will continue to perform storm drain improvement work on Ethanac Road. Traffic control will be set up and flaggers will be present. Motorists should expect delays. Storm drain improvements are expected to be completed at the end of September 2025.
For a current list of all street projects and construction updates, visit our interactive mobile and web map at www.cityofmenifee.us/traffic.