The City will perform fog seal (asphalt rejuvenation) on neighborhood streets beginning Tuesday , September 2nd . Work will be done one side of the street at a time -there will be no full road closures , and access will be maintained.
Timbertop Drive Phasing Map
Scarteen and Rolling Oaks Trail Phasing Map
Phase 1 (blue) September 4th
Phase 2 (red) September 5th
Phase 3 (yellow) September 8th
Phase 4 (green) September 9th
How to Prepare
Remove parked vehicles from the street on your phase day and the following day (for sweeping).
Avoid sprinklers for 2-3 days after treatment.
Please keep children and pets off treated areas until sanded.
If possible, avoid driving over treated areas until sand is down.
Any product spotting on vehicles can be cleaned with citrus-based or standard car-care cleaners.
Thank you for your patience as we complete this important street maintenance.