What: Weather permitting, the Georgia Department of Transportation (Georgia DOT) construction partners will temporarily close interstate lanes at the locations below for the
I-285/I-20 East Interchange project. The project will reconstruct the interstate system-to-system ramps at the I-285/I-20 East Interchange and add a combination of collector-distributor (CD), or connecting lanes, and auxiliary lanes along I-20 east of the interchange and I-285 north of the interchange.
Where/When: Traffic impacts on the I-285/I-20 Interchange project from Friday, September 19, through Friday, September 26, 2025.
DAYTIME CLOSURES:
Friday, September 19, through Friday, September 26, from 9 a.m. to 2 p.m.
-
I-20 Eastbound: Single, right- or left-lane and shoulder closure from Wesley Chapel Road (MM 69.5) to Panola Road (MM 71.3)
-
I-20 Eastbound: Single, right- or left-lane and shoulder closure from Columbia Drive (MM 66.8) to Wesley Chapel Road (MM 69.5)
-
I-20 Eastbound (connecting lanes or CD lanes): Single, right- or left-lane and shoulder closure from I-285 Interchange (MM 67.3) to Wesley Chapel Road (MM 69.5)
Friday, September 19, through Friday, September 26, from 9 a.m. to 4 p.m.
-
Hillandale Drive at DeKalb Medical Parkway Flagging operation
Friday, September 19, through Friday, September 26, from 9 a.m. to 4 p.m.
-
Miller Road over I-20 Flagging operation
OVERNIGHT CLOSURES AND TRAFFIC PACING:
Friday, September 19, through Friday, September 26, from 7 p.m. to 6 a.m.
-
I-20 Eastbound: Single to double, right- or left-lane and shoulder closure from Wesley Chapel Road (MM 69.5) to Panola Road (MM 71.3)
-
I-20 Eastbound (connecting lanes or CD lanes): Single to double, right- or left-lane and shoulder closure from I-285 Interchange (MM 67.3) to Wesley Chapel Road (MM 69.5)
-
I-20 Eastbound: Single to double, right- or left-lane and shoulder closure from Columbia Drive (MM 66.8) to Wesley Chapel Road (MM 69.5)
-
I-20 Eastbound: Alternating, single, left- and right-lane and shoulder closures from Wesley Chapel Road (MM 68.5) to Panola Road (MM 71.4)
-
I-20 Eastbound to I-285 Northbound alternating single, left- and right-lane closure
-
I-20 Eastbound: Single, right-lane closure on Wesley Chapel off-ramp
Friday, September 19, through Friday, September 26, from 8 p.m. to 6 a.m.
-
I-285 Southbound: Single to double, left- or right-lane closure from Interchange to Columbia Drive
-
I-285 Southbound: Single to double, right-lane and shoulder closures from Glenwood to interchange
-
I-285 Northbound: Single to double, left- or right-lanes and shoulder closure from Columbia to interchange
Friday, September 19, through Friday, September 26, from 9 p.m. to 6 a.m.
-
I-20 Westbound: Single to double, right- or left-lane and shoulder closure from Panola Road (MM 71.3) to Wesley Chapel Road (MM 69.5)
-
I-20 Westbound: Single to double, left-lane closure from Wesley Chapel Road (MM 69.5) to Columbia Drive (MM 66.8)
-
I-20 Westbound: Alternating, single, left- and right-lane and shoulder closure from Panola Road (MM 71.4) to Wesley Chapel Road (MM 68.5)
CLOSURES AND DETOURS:
A temporary closure will be in place on East Wesley Chapel Way from the 1st Place Hotel entrance to the Capital Finance Entrance. During this time all through traffic should use Snapfinger Woods Drive.The closure will remain in effect through October 8.
|
Activity
|
Start Date
|
End Date
|
Times
|
I-20 Westbound
|
-
I-20 from Panola Road to Wesley Chapel Road
|
Single to double, right- or left-lane and shoulder closure
|
September 19
|
September 26
|
9 p.m. - 6 a.m.
|
-
I-20 from Panola Road to Wesley Chapel Road
|
Alternating, single, left- and right-lane and shoulder closures
|
September 19
|
September 26
|
9 p.m. - 6 a.m.
|
-
I-20 from Wesley Chapel to Columbia Drive
|
Single to double, left-lane closure
|
September 19
|
September 26
|
9 p.m. - 6 a.m.
|
-
I-20 from Panola Road to the I-285 Interchange, including Wesley Chapel entrance ramp
|
Traffic pacing operation
|
September 19
|
September 26
|
9 p.m. - 6 a.m.
|
-
I-20 westbound Wesley Chapel Road to Columbia Drive
|
Traffic pacing operation
|
September 19
|
September 26
|
9 p.m. - 6 a.m.
|
I-20 Eastbound
|
-
I-20 from Wesley Chapel Road to the Panola Road
|
Single, right-lane and shoulder closure
|
September 19
|
September 26
|
9 a.m. - 2 p.m.
|
-
I-20 connecting (CD) lanes from the I-285 Interchange to Wesley Chapel Road
|
Single, right-lane and shoulder closure
|
September 19
|
September 26
|
9 a.m. - 2 p.m.
|
-
I-20 from Columbia Drive to Wesley Chapel
|
Single, right- or left-lane and closure
|
September 19
|
September 26
|
9 a.m. - 2 p.m.
|
-
I-20 from Wesley Chapel Road to Panola Road
|
Single to double, right-or left-lane and shoulder closure
|
September 19
|
September 26
|
7 p.m. - 6 a.m.
|
-
I-20 connecting (CD) lanes from the I-285 Interchange to Wesley Chapel Road
|
Single to double, right- or left-lane and shoulder closure
|
September 19
|
September 26
|
7 p.m. - 6 a.m.
|
-
I-20 Columbia Drive to Wesley Chapel Road
|
Single to double, right- and left-lane and shoulder closure
|
September 19
|
September 26
|
7 p.m. - 6 a.m.
|
-
I-20 From Wesley Chapel Road to Panola Road
|
Traffic shift in all eastbound lanes
|
September 19
|
September 26
|
7 p.m. - 6 a.m.
|
-
I-20 Eastbound to I-285 Northbound
|
Alternating single, left-and right lane closures from
|
September 19
|
September 26
|
7 p.m. - 6 a.m.
|
-
I-20 Eastbound closure on Wesley Chapel off-ramp
|
Single, right-lane closure
|
September 19
|
September 26
|
8 p.m. - 6 a.m.
|
I-285 Southbound
|
|
|
|
|
-
I-285 Southbound from Interchange to Columbia Drive
|
Single to double, left- or right-lane closure
|
September 19
|
September 26
|
8 p.m. - 6 a.m.
|
-
From Glenwood Road to the I-20 Interchange
|
Single to double, and right-lane and shoulder closures
|
September 19
|
September 26
|
8 p.m. - 6 a.m.
|
I-285 Northbound
|
|
|
|
|
-
From Columbia Drive to the I-20 Interchange
|
Single to double, left- or right-lanes and shoulder closure
|
September 19
|
September 26
|
8 p.m. - 6 a.m.
|
-
I-20 from Wesley Chapel Road to Panola Road
|
Alternating, single, left- and right-lane and shoulder closure
|
September 19
|
September 26
|
8 p.m. - 6 a.m.
|
|
|
|
|
|
Flagging Operation
|
|
|
|
|
Miller Road over I-20
|
Flagging Operation
|
September 19
|
September 26
|
9 a.m. - 4 p.m.
|
Hillandale Drive at DeKalb Medical Parkway
|
Flagging Operation
|
September 19
|
September 26
|
9 a.m. - 4 p.m.
|
Closures
|
|
|
|
|
East Wesley Chapel Way near Snapfinger Woods Drive
|
Temporary Closure
|
September 19
|
October 8
|
|
|
|
Advisory: Exact time may change due to weather conditions. Motorists are advised to expect delays, exercise caution, and reduce their speed while traveling through work zones, stay alert, and watch for workers. Before heading out, get real-time information on work status and traffic conditions. Call 511, visit 511ga.org, or download the Georgia 511 app.
|
|
|