Sept. 22 - 28, 2025
JEFFERSON CITY , Mo. - The following is a list of general highway maintenance and construction work planned in the mid - Missouri area Sept . 22 - 2 8 , 202 5 . Weather conditions may postpone scheduled work. Many projects will include lane closures which could cause delays.
All Counties
Other m oving operations such as pothole patching, mowing , and pavement repair s continue in various locations. Motorists should travel with care and be alert for slow - moving equipment.
All work is weather permitting, and schedules are subject to change.
Boone County
Route s B and NN - Pavement repairs planned Sept. 22 - 25 . One lane will remain open, and crews will flag traffic through the work zone.
Missouri Routes 740 and Route 163 intersection - Signal cabinet upgrades scheduled Sept. 25. The signals at Stadium Boulevard and Providence Road will be turned off at midnight. Stop signs will be in place and motorist should treat the intersection as a 4-way. Crews expect to have the signals operational by 6 a.m. the same day.
Route TT - Pedestrian facility upgrades continue from Yorkshire Drive to Fairview Road . Work will require temporary closures of pedestrian facilities and intermittent single-lane closures with flaggers to direct motorists through the work zone. The project is scheduled for completion in September 2025.
Route K and Old Plank Road intersection - Roundabout construction continues . The intersection will remain open,but is narrowed to one lane with temporary traffic signals directing motorists through the work zone . Motorists should expect delays. This is a cost share project between the City of Columbia and MoDOT. The project is scheduled for completion in December 2025.
U.S. Route 63 - Interchange improvements at Route AC (Grindstone Parkway) continue . Northbound t raffic is narrowed from Sugar Grove Road to approximately 1 mile north of Grindstone Parkway . A 10- foot width restriction is in place . The project is expected to continue through November 2026 .
U.S. Route 63 - Bridge rehabilitation continues between Broadway (south of Interstate 70) and Vandiver Drive (north of I-70) in Columbia. The roadway will remain open but in a head-to-head configuration with narrowed lanes and reduced speeds. This traffic pattern is expected to be in place through November 2025. This work is part of the Improve I-70 program. Learn more at modot.org/improvei70/columbiakingdomcity.
I -70 - New p avement construction continues between Route B (Paris Road) and U.S. Route 63 as part of the Improve I-70 Program . Motorists can expect intermittent and long-term lane closures for the duration of the project , which is expected to be complete in 2027 . Learn more at modot.org/improvei70/ columbiakingdomcity .
North Outer Road 70 - CLOSING Sept. 25 for a culvert extension project at Little Cedar Creek, east of Columbia near mile marker 134.8 on I-70. Motorists will need to use an alternate route during the closure, which is expected to continue through February 2026.
Callaway County
Route J - Pavement resurfacing continues . One lane will remain open with a 10-foot width restriction, and flaggers with a pilot car will direct motorists through the work zone. The project is scheduled for completion in Octo ber 2025.
South Outer Road 70 (Jade Road) and North Outer Road 70 (Old U.S. Route 40) - CLOSED for a c ulvert replacement project at Sallees Creek , west of Kingdom City . Motorists will need to use an alternate route during the closure s , which are expected to continue through February 2026.
I-70 - New pavement construction continues from the Boone County line (near mile marker 13 6.6) to Kingdom City (near mile marker 14 8 ) as part of the Improve I-70 Program.Motorists can expect intermittent and long-term lane closures for the duration of the project, which has an overall completion date in 2027. Learn more at modot.org/improvei70/columbiakingdomcity
I-70 w estbound ramps - The ramps to and from Route J (Exit 137) are CLOSED . As an alternate route, motorists can take Exit 144 and use the North Outer Road 70 to Route J. To continue westbound on I-70 from Route J, motorists can take the North Outer Road 70 to Exit 133. The South Outer Road 70 is not continuous and does not connect to Route J.
Camden County
Missouri Route 5 - Pavement striping planned Sept. 22 - 25 from the city limits of Lebanon to Camdenton. One lane will remain open, and crews will flag traffic through the work zone.
Route H - Pavement resurfacing continues . One lane will remain open with a 10-foot width restriction , and flaggers with a pilot car will direct motorists through the work zone. The project is scheduled for completion in September 2025.
Route JJ - Pavement resurfacing continues . One lane will remain open with a 10-foot width restriction , and flaggers with a pilot car will direct motorists through the work zone. The project is scheduled for completion in October 2025.
Cole County
Route E - Resurfacing continues . One lane will remain open, and flaggers with a pilot car will direct motorists through the work zone. The project is scheduled for completion in September 2025.
Route W - Pedestrian facility upgrades continue from Route B to Churchview Heights . Work will require temporary closures of pedestrian facilities and intermittent single-lane closures with flaggers to direct motorists through the work zone. The project is scheduled for completion in September 2025.
Missouri Boulevard - Pedestrian facility upgrades scheduled to begin Sept. 23 from H owerton Court to Wildwood Drive . Work will require temporary closures of pedestrian facilities and intermittent nighttime single-lane closures. The project is scheduled for completion in October 2025.
U.S. Route 54 Westbound - Bridge rehabilitation continues over Moreau River Drainage, south of Jefferson City. The road is narrowed to one lane with an 11-foot width restriction and speed reductions are in place through the work zone. The project is scheduled for completion in October 2025.
Associated access restriction through October 2025:
U.S. Route 54 - Bridge replacement continues over Neighorn B ranch , south of Jefferson City . Traffic is narrowed to one lane in each direction and in a head-to-head configuration for the duration of project. A 14-foot width restriction and speed reductions as low as 45 mph are in place through the work zone. The project is scheduled for completion in November 2025.
Associated access restrictions through November 2025:
U.S. Route 54 - Bridge replacement continues over Vetter Lane. Traffic is narrowed to one lane in each direction and in a head-to-head configuration for the duration of project. A 12-foot width restriction and speed reductions are in place through the work zone. The project is scheduled for completion in December 2025.
Associated access restrictions through December 2025:
Crawford County
Route J - Bridge replacement continues over B oone Creek . The bridge is CLOSED with a signed detour is in place to direct motorist s around the closure. The project is scheduled for completion in December 2025.
Gasconade County
Missouri Route 19 - Pavement resurfacing continues from U.S. Route 50 to the Crawford County line. One lane will remain open, and flaggers with a pilot car will direct motorists through the work zone. The project is scheduled for completion in October 202 5 .
Howard County
Route 5 - Bridge replacement continues over Bear Creek in Glasgow . One lane will remain open, and temporary traffic signals will direct motorists through the work zone. A 1 2 -foot width restriction is in place. The project is scheduled for completion in October 2025.
Laclede County
Route 5 - Pavement striping planned Sept. 22 - 25 from Lebanon to the city limits of Camdenton. One lane will remain open, and crews will flag traffic through the work zone.
South Outer Road 44 - CLOSED for a b ridge rehabilitation over Bear Creek near Exit 135 . M otorist s must use an alternate route. The project is scheduled for completion in September 2025.
Route JJ - Pavement resurfacing continues . One lane will remain open with a 10-foot width restriction , and flaggers with a pilot car will direct motorists through the work zone. The project is scheduled for completion in October 2025.
Route E - Resurfacing continues . One lane will remain open, and flaggers with a pilot car will direct motorists through the work zone. The project is scheduled for completion in November 2025.
Maries County
Missouri Route 4 2 - Pavement repairs planned Sept. 22 - 25 from Route T to the city limits of Vienna . One lane will remain open, and crews will flag traffic through the work zone.
Route C - Culvert replacement planned Sept. 22 - 25 . One lane will remain open, and crews will flag traffic through the work zone.
Route H - Pavement repairs planned Sept. 22 - 25. One lane will remain open, and crews will flag traffic through the work zone.
Route AA - Bridge replacement continues over the Little Maries River. The bridge is CLOSED with a signed detour in place. The project is scheduled for completion in November 2025.
Miller County
Route s 87 and FF - Pavement repairs planned Sept. 22 - 25 . One lane will remain open, and crews will flag traffic through the work zone.
Mo niteau Count y
Route K - Pavement repairs planned Sept. 22. One lane will remain open, and crews will flag traffic through the work zone.
Business Route 50 - Pavement repairs planned Sept. 23 - 25 from U.S. Route 50 to Lookout Trail Road. One lane will remain open, and crews will flag traffic through the work zone.
Route U - Bridge replacement continues over Howard Creek. The bridge is CLOSED, and m otorist s will need to seek an alternate route. The project is scheduled for completion in November 2025.
Route 87 and Route C intersection - Roundabout construction continues . The intersection will remain open, but is narrowed to one lane with temporary traffic signals directing motorists through the work zone . Motorists should expect delays. The project is scheduled for completion in November 2025.
Morgan County
Route 52 - Roundabout construction continues in Versailles at the intersection of Route 52 and Route 5 . One lane will remain open, and crews will flag traffic through the work zone. The project is scheduled for completion in November 2025 .
Osage County
Missouri Route 89 - Pavement repairs planned Sept. 22 - 25 from U.S. Route 50 to the city limits of Belle. One lane will remain open, and crews will flag traffic through the work zone.
Route C - Culvert replacements planned Sept. 22 - 25. One lane will remain open, and crews will flag traffic through the work zone.
Route T - Sealing operations continue . One lane will remain open, and flaggers with a pilot car will direct motorists through the work zone. The project is scheduled for completion in September 2025.
Phelps Count y
Missouri Route 68 - Shoulder work planned Sept. 22 - 25 at County Road 3480. One lane will remain open, and crews will flag traffic through the work zone.
Route BB - Shoulder work planned Sept. 22 - 25 between County Road 3110 and Vintage Lane. One lane will remain open, and crews will flag traffic through the work zone.
Route BB - Culvert replacement planned Sept. 22 - 25 at Edmonson Hills Drive. One lane will remain open, and crews will flag traffic through the work zone.
Outer Road 44 (Vineyard Road) - Pavement repairs planned Sept. 22 - 25 from Route U to the Crawford County line. One lane will remain open, and crews will flag traffic through the work zone.
U.S. Route 63 - Turn lane installation continue approximately 1 mile south of Route W . Work is being done by Courtney Construction Company under a MoDOT-issued permit. One lane will remain open with an 11-foot width restriction in place. The project is scheduled for completion in September 2025.
Route D - Bridge rehabilitation continues over I-44, approximately 7 miles southwest of Doolittle. The bridge is CLOSED , with a signed detour in place. The project is scheduled for completion in October 2025.
Missouri Route 72 and Route KK - Pedestrian facility upgrades continue on Route 72 in Rolla and Route KK in St. James . Work will require temporary closures of pedestrian facilities and intermittent single-lane closures with flaggers to direct motorists through the work zone . The project is scheduled for completion in November 2025.
Pulaski County
Missouri Route 133 - Culvert replacements planned Sept. 22 - 25 from Route BB to Rose Finch Road . One lane will remain open, and crews will flag traffic through the work zone.
Missouri Route 28 - Bridge rehabilitation continues over I-44 in St. Robert. The bridge is CLOSED , with a signed detour in place. The project is scheduled for completion in October 2025 .
Washington Cou nt y
Route 8 - Bridge rehabilitation continues over the Union Pacific Railroad. The roadway will remain open throughout the project but is narrowed to one lane. Motorists s hould expect delays.
Route C - CLOSED for a bridge replacement project over Big River . A signed detour is in place to direct motorist around the work zone. The project is scheduled for completion in October 2025.
Missouri Route 47 - Bridge replacement continues over Mill Creek. The bridge is CLOSED with a signed detour in place to direct motorists around the closure. This project is scheduled for completion in November 2025.
MoDOT asks all motorists to work with us by buckling up, putting your phone down, obeying all traffic signs, and slowing down and moving over in work zones.
For more information about MoDOT projects, traffic updates, or other transportation-related matters, please visit our Traveler Information Map at http://traveler.modot.org/ o r call our 24-hour Customer Service Center at 1-888-ASK-MoDOT (888 275-6636). While at modot.org, sign up for work zone updates sent directly to your inbox. Information is also available 24/7 by connecting with us on social media: