09/11/2025 | Press release | Distributed by Public on 09/11/2025 10:19
Anderson County
Palestine crews are scheduled to perform repairs on FM 3309 as well as FM 1892. Motorists should expect lane closures with flaggers controlling traffic.
Anderson County construction projects updates:
US 175 Widening Project
Traffic is currently being switched to the new pavement on the westbound lane, while the contractor works on the eastbound lane. The contractor is currently building the new eastbound roadbed. The contractor is also constructing driveways and ditches. They are also scheduled to continue working on the bridge deck and rail on the eastbound bridge. The contractor will also finalize ditches and slopes. The project consists of expansion to a four-lane roadway with new bridges across the Neches River.
----------------------------------------
Cherokee County
Cherokee County construction projects updates:
US 175 Widening Project
The following county road intersections will be closed within the project limits:
The contractor is scheduled to continue work on the eastbound side through Cuney. Preparation of the right of way on the westbound side will also continue on the westside of the road. The contractor is also scheduled to continue drainage work, bridge work, and clearing utilities. Motorists should use caution when traveling through the work limits. The speed limit has been reduced to 55 mph throughout the project limits. The project consists of expansion to a four-lane roadway with new bridges, grading, asphalt, drainage structures, pavement markings, and signage. (This project is located in Cherokee County but is managed by the Athens Area Office.)
SH 204
This week, the contractor is scheduled to continue laying asphalt, placing topsoil, and seeding. Crews will also continue SW3P operations. Motorists should drive with caution in the work zone. Lane closures are anticipated. This project consists of adding a super-two highway section.
US 79
The contractor is scheduled to lay rumble strips a begin cutting bridge joints. The speed limit has been reduced to 55 mph throughout the project limits. This project consists of rehabilitation of the existing road, including pavement repair, resurfacing, metal beam guard fence, and pavement markings.
SH 110
No work scheduled this week. This project is a change order to a bridge preventative maintenance project that consists of installing a temporary soil nail wall and a permanent retaining wall to address slope failure on SH 110. Motorists should drive with caution when work is in progress.
US 69 and FM 2493 Grade Separated Interchange Realignment
The contractor is has a planned lane closure on US 69 in the northbound, outside lane through the project limits. Motorists should drive with caution. The project consists of a grade separated interchange and realignment of FM 2493 West of US 69.
----------------------------------------
Gregg County
Longview crews are scheduled to continue mill and inlay operations on US 259 N. The work will be done in the north and southbound lanes from US 80 to Young St. Motorists should expect lane closures while work is in progress.
Gregg County construction projects updates:
US 80
The project consists of removing four inches of existing surface and replacing with new hot mix. The project will also include striping and pavement markings. This week, the contractor is scheduled to lay new asphalt.
Young St. - City of Longview
This project consists of constructing sidewalks and handicap accessible ramps on both sides of Mobberly Ave. This week, the contractor will be clearing right of way and pouring concrete for the sidewalk on the north side of the street. If completed, crews will then switch to the south side of the street.
SH 135 - Kilgore Traffic Circle
This project involves rebuilding the traffic circle and the entire width of the roadway to the Rusk County line. This week, crews are scheduled to place the final striping and work on punch list items.
I-20 Resurfacing
This project consists of milling asphalt off the surface and placing new hot mix asphalt from the Sabine River bridge to the Harrison County line. Work will be done in both the east and westbound lanes. Work is scheduled to be performed during overnight hours. One lane will be closed at a time. The contractor is scheduled to lay asphalt beginning Sunday night, September 14th. The work will be alternated from the east and westbound lanes.
----------------------------------------
Henderson County
Athens crews will be performing overlay on FM 2613. Motorists should expect lane closures with flaggers controlling traffic. Also, crews will perform sign maintenance, pothole repair, and herbicide operations at various locations throughout the county.
Henderson County construction projects updates:
FM 316 Rehabilitation
The project is in time suspension and awaiting final acceptance. The project includes pavement reconstruction, structures, pavement markings and signs.
FM 315 Rehabilitation
The contractor currently performing edge work at various locations throughout the project limits. There should be no impact to traffic. The project includes pavement reconstruction, structures, pavement markings and signs.
BUS 19 Sidewalks
The contractor is placing concrete for the sidewalks and driveways on the west side of the road. Motorists should expect lane closures while work is in progress. This project includes sidewalk and pedestrian lane improvements.
SH 19 Super 2 Project
The contractor has begun cement treating for roadway widening in the southbound lane. The speed limit is reduced to 60 mph throughout the project limits. This project includes adding a passing lane in each direction at multiple locations. It also includes grading, drainage structures, pavement markings, and signage.
BUS 31 Rehabilitation
Nighttime operations are scheduled to continue this week. Motorists should expect lane closures. The project includes removal of current surface, base repairs, resurfacing, striping, and signage. Traffic should use caution when traveling through the work zone at night and expect pavement striping operations during the day.
SH 31 at Sawmill Rd.
The new traffic signal is operational. This project consists of installing a traffic control signal and pedestrian signal.
----------------------------------------
Rusk County
Henderson crews are scheduled to repair base failures and repair edges on FM 1798. Motorists should expect lane closures with flaggers controlling traffic. Contractor crews are also scheduled to trim and remove trees at various locations.
Rusk County construction projects updates:
US 84 - FM 225 East to CR 3155
This project consists of reconstructing US 84, extended structures, hot mix asphalt surface, new signs, and striping. This week, the contractor will be sealcoating the road. Motorists should expect alternating lane closures.
SH 315
This project consists of widening pavement edges and installing space between the traffic lanes to separate opposing traffic for safety. Work will also include adding one passing lane in each direction of travel. This week, the contractor is scheduled to lay asphalt. Motorists should expect alternating lane closures. Crews will also perform striping and guard fence installation.
FM 2658
This project consists of reconstructing FM 2658 completely, from CR 344 to FM 1251. Work includes a new guard fence, treating subgrade, base material, seal coat, and striping. This week, the contractor is scheduled place asphalt and sealcoat.
US 79 N
This project consists of repairing slope failure in the TxDOT right of way. The site will be excavated, and a new embankment will be placed. This week, the contractor will be working on punch list items. Work will mostly be off of the roadway.
SH 43
This project consists of milling approximately six inches off the surface and replacing it with new hot mix. The project also includes clearing the right of way, replacing driveway pipes, and striping. This week, the contractor is scheduled place final striping and working on the edge of the pavement. Expect lane closures with flaggers controlling traffic.
----------------------------------------
Smith County
Tyler Maintenance crews are continue working on ditch and drainage issues. Expect lane closures with flaggers controlling traffic. Contract mowing is expected to begin on Monday, Sept. 15.
Smith County construction projects updates:
US 69 Rehab Existing Road and Restricted Crossing U-Turn (R-Cut)
The contractor is scheduled to clean and seal the bridge joints at the Mudd Creek bridge. This work will be done during daytime hours. No lane closures are expected. This project consists of rehabilitating existing roadway and installing a restricted crossing U-turn (R-Cut) at FM 2813 intersection.
SH 31 Safety Improvements
The contractor has no work scheduled this week. Motorists should drive with caution in the work zones. The project consists of safety improvements, including installation of cable and concrete median barriers.
FM 2493 Widen Non-Freeway
The contractor has scheduled daily lane closures from 8:15a to 6p from S. Kimberly Dr. to CR 150. Motorists should plan ahead and drive with caution. This project consists of widening the existing non-freeway roadway.
I-20 Bridge Maintenance
The contractor has no work scheduled this week. This project is bridge maintenance, consisting of cleaning and painting existing steel bridge superstructures.
Pedestrian Sidewalks & Curb Ramps
This work will be at various locations throughout the Tyler city limits. The contractor will be pouring concrete and preparing to move to the intersection of Glenwood and Front Street. Motorists should drive with caution. Lane closures are possible. The project consists of upgrading pedestrian safety measures at various intersections.
Smith County Bridge Rehabilitation
The contractor is scheduled to remove material beneath the US 175 and SL 7 bridge. This project consists of cleaning and sealing the existing bridge joints, asphalt work, resurfacing the bridge deck, installation of new metal beam guard fence, steel and concrete repairs.
I-20 Bridge Maintenance
Beginning Tuesday, Sept. 2, there will be temporary traffic lights installed on CR 496 at I-20. One lane will remain open at all times. Crews are also scheduled to work on the CR 496 bridge. This project is bridge maintenance consisting of cleaning and painting the existing steel bridge structures.
FM 16 Widening and Realignment
The project consists of grading, asphalt base, asphalt surface overlay paving, storm drain, bridge, and culvert structures, signing, pavement markings, and signals. A traffic shift is currently in place through town. Traffic will be in two lanes during this phase of construction. Embankment installation is ongoing. Crews are also scheduled to prepare surface for seal coat treatment. Bridge work is also ongoing. (This project is located in Smith County but is managed by the Mineola Area Office.)
SH 31 Resurfacing
Overlay operations have been completed. Contractor will make any additional repairs if needed. The project is scheduled to be completed on Wednesday, Sept. 17. The project includes prep row, base repairs, resurfacing, striping, and signage. Motorists should use caution when traveling through area and expect delays. (This project is located in Smith County but is managed by the Athens Area Office.)
---------------------------------------
Van Zandt County
Canton crews are scheduled to pick up debris at various locations throughout the county. Lane closures are possible, so watch for flaggers. Also, crews are scheduled to perform base repairs on FM 1504 in preparation for seal coat application. Crews will also continue herbicide operations.
Van Zandt County construction projects updates:
FM 17, FM 47, and FM 859 Bridge Replacement
This project is for the construction of a new bridge and approaches, grading, base and surface, and metal beam guard fence installation. Motorists should expect work zone speed limit reductions and shoulder width reductions on the I-20 main lanes. Motorists should also expect work zone speed limit reductions and shoulder width reductions on the I-20 frontage roads. On FM 17, crews are scheduled to place new asphalt on the westbound frontage road. The ramp will be closed to traffic. On FM 47, crews are scheduled to install the traffic rail and install flex base on the eastbound frontage road. Motorists should expect daily lane closures in this area. On FM 859, crews are scheduled to complete work on the concrete barrier and asphalt surface. New traffic configuration is scheduled to take place on Friday, Sept. 5.
FM 1255 Rehabilitate Existing Roadway
This project is for the rehabilitation of the existing roadway consisting of roadway widening, grading, rework base material, cement treatment, flex base, TCST, resurfacing intersections & driveways, extending cross structures, signs, and pavement markings. The project will be completed under traffic. Right of way prep and tree trimming are ongoing. Roadway rehabilitation operations and cross structure installation are ongoing pending weather. This work also consists of milling the existing roadway. Lane closures and speed zone reductions are expected. Motorists should expect delays.
I-20 WB Exit Ramp at SH 19
This project consists of ramp improvements. Crews have initiated construction on the drainage structures and frontage road alignment. Crews are scheduled to sealcoat over the new paved section, followed by striping operations. Closeout items will soon follow.
SH 64 at I-20 and SH 155 at I-20 Traffic Signal Installation
The project includes the construction and installation of traffic control devices including pedestrian signals. The SH 64 intersection striping layout has been completed. SH 155 intersection signals are complete and functioning. The frontage roads between SH 155 and Lawhon Ave. have been converted to one-way travel only. Major items and punch list items have been addressed. Project is awaiting final acceptance.
FM 1651 Rehabilitate Existing Roadway
Construction is still underway on the cross structures and headwalls. This project is focused on fixing and improving the existing road. Work includes widening the road, repairing the base, adding signs, and painting new stripes. Crews will finish groundwork in one-mile segments. Drivers should expect lane closures and slower speed limits in the area. Delays are likely, so please plan ahead. (This project is located in Van Zandt County but is managed by the Athens Area Office.)
FM 279 Rehabilitation
The contractor is scheduled to perform edgework throughout the project limits. Motorists should expect delays and use caution when traveling through the area. Lane closures are in place. The project consists of pavement repair, grading ditches, drainage structures, asphalt, striping, and signage. (This project is located in Van Zandt County but is managed by the Athens Area Office.)
E Tyler St. at Mill Creek Bridge
This project is for bridge replacement, new approaches, grading, and base repairs. The contractor is nearing completion and is working on closeout items. E. Tyler Street is closed to through traffic.
---------------------------------------
Wood County
This week, crews are scheduled to overlay on FM 17 between US 69 and the Sabine River. Traffic will be controlled by flaggers and a pilot car. Also, crews will perform edge work on FM 2088 from SH 37 to the Upshur County line. Expect lane closures with flaggers controlling traffic. Also, crews will apply herbicide at various locations and conduct bridge inspection and maintenance at various locations throughout the county.
Wood County construction projects updates:
US 69 Grade-Separated Interchange
This project consists of grading, base, asphalt, drainage, structures, overpass, signing, and striping. There will also be curb and gutter work on the frontage road sections. Also, crews are preparing foundations for the retaining wall. Crews are scheduled to place temporary paving at the FM 779 intersection on the west side. Crews are also scheduled to work on the retaining walls. Motorists should be cautious of large equipment in the work zone. Lane closures are expected. Motorists should expect delays.
----------------------------------------
I-20 Total Maintenance Contract