Resurfacing Update: June 4, 2026

BLOOMINGTON, IL - The City of Bloomington provides regular updates on resurfacing work throughout the construction season. The most recent update is included below.

For more information on roadwork in the City of Bloomington, visit www.bloomingtonstreets.com, e-mail [email protected] or call 309-434-2980 during regular business hours. Residents can also sign up for e-mail or text updates for Bloomington Streets by visiting www.bloomingtonil.gov/subscribe and subscribing to Bloomington Streets.

FY26 Resurfacing

E. Oakland Ave, west of Prospect through Hershey

  • Installation of the pavement striping has been completed
  • A final inspection and clean-up is in progress

Prospect Rd, Oakland to Empire

Stage 1: S. Prospect Rd. (Oakland to Washington)

  • Installation of the pavement striping has been completed
  • A final inspection and clean-up is in progress

Stage 2: N. Prospect Rd. (Washington to Empire)

  • Installation of the pavement striping has been completed
  • A final inspection and clean-up is in progress

E. Washington St, Veterans through Hershey

  • Installation of the pavement striping has been completed
  • A final inspection and clean-up is in progress

FY27 Resurfacing

Eastland Dr, Fairway to Hershey

Stage 1: Fairway to Veterans

  • This section will be started after the completion of St. Joseph Drive
  • The limits and layout of the work zone has been completed

Stage 2: Veterans to Hershey

  • The limits and layout of the work zone has been completed
  • Underground utility locations have been requested
  • Installation of traffic control has been completed
  • Removal of the underground utility castings is in progress
  • Removal and replacement of the underground utility work is in progress
  • Removal and replacement of the concrete items (curb & gutter, sidewalks) is in progress
  • Removal (milling) of the asphalt surface has been scheduled to start June 9

St. Joseph Dr, Washington to Eastland

  • The limits and layout of the work zone has been completed
  • Underground utility locations have been requested
  • Installation of traffic control has been completed
  • Removal of the underground utility castings is in progress
  • Removal and replacement of the underground utility work has been completed
  • Removal and replacement of the concrete items (curb & gutter, sidewalks) is in progress
  • Removal (milling) of the asphalt surface has been scheduled to start June 9

Four Seasons Rd, Oakland through the cul-de-sac

  • The limits and layout of the work zone has been completed
  • Underground utility locations have been requested
  • Installation of traffic control has been completed
  • Removal of the underground utility castings is in progress
  • Removal and replacement of the underground utility work has been scheduled
  • Removal and replacement of the concrete items (curb & gutter, sidewalks) is in progress

Contact:
Katherine Murphy
Communications & External Affairs Mgr.
Phone: 309-434-2241
Email: [email protected]

Contact:
Jim Karch
Director of Engineering
Phone: 309-434-2980
E-mail: [email protected]

City of Bloomington, IL published this content on June 04, 2026, and is solely responsible for the information contained herein. Distributed via Public Technologies (PUBT), unedited and unaltered, on June 04, 2026 at 15:57 UTC. If you believe the information included in the content is inaccurate or outdated and requires editing or removal, please contact us at [email protected]