September 23, 2025
The City appreciates your ongoing patience with the work associated with this project. Additional information regarding this project can be found at www.DurhamNC.gov/5386
Here's the schedule for the next two weeks:
Week of September 22-26 - work at Peachtree Place, Liberty Street, and Albany Street
Peachtree Place Traffic Control Plan
Liberty Street Traffic Control Plan
-
Peachtree Place
-
Peachtree Place 8" WL Install
-
Liberty Street - 16" WL BACT Samples
-
Peachtree Place & Liberty & Albany Street
-
Peachtree Place 8" WL Install
-
Direct Tap Ex. WL on Peachtree for Blowoff Point on test shutdown
-
Liberty Street - 16" WL BACT Samples
-
Final Paving Albany Street Mill & Overlay
-
Peachtree Place
-
Peachtree Place 8" WL Install
-
Peachtree Place 8" Gate Valve Install
-
Peachtree Place
-
Peachtree Place 8" WL Install
-
Shoot 8" Pig on Peachtree Place
-
Peachtree Place
-
Finish Peachtree Place 8" WL
-
Shoot 8" Pig - Peachtree
-
Prep for Night work inside NCDOT ROW
Week of September 26-October 3 - work at Peachtree Place & Liberty Street
-
Peachtree Place & Liberty
-
Liberty Street - 16" WL Tie in
-
BACT Samples Peachtree Place
-
(Apartment Entrance Detour)
-
Tue, Sep 30th - Peachtree Place & Liberty
-
Liberty Street - 16" & 6" WL Tie in
-
BACT Samples Peachtree Place
-
(Apartment Entrance Detour)
-
Wed, Oct 1st - Liberty Street
-
Liberty Street - 16" WL Tie in
-
Thu, Oct 2nd - Liberty Street
-
Liberty Street - 16" WL Tie in
-
Fri , Oct 3rd - Liberty Street
-
Asphalt Trench Repairs Liberty Street
-
NLT Install Changeable Message Board Sign on Holloway
For more information, visit the project's webpage at www.DurhamNC.gov/5386