11/16/2026 | Press release | Distributed by Public on 11/16/2026 08:05
Fast facts:
MARSHALL, Mich. - The Michigan Department of Transportation (MDOT) is pausing work the week of Nov. 16 on the Marshall Modernization Project in support of the Marshall Area Jobs, Opportunity and Recreation (MAJOR) Campus.
Until work resumes in the spring, there will be one lane open in each direction on M-96 (Michigan Avenue) and M-311 (11 Mile Road). There will be two lanes open in each direction of I-94, and all ramps at Exit 104 will be open.
2026 was the second year of this three-year, $335 million investment. Work accomplished this year includes:
Work in 2027 is expected to start in March with the demolition of the M-311 bridge over I-94 to start bridge reconstruction. Other work in 2027 will include rebuilding eastbound I-94 and eastbound ramps at Exit 104, completing the M-96 boulevard conversion, and rebuilding the Pigeon Creek box culvert under M-96.