Lane Closure Advisory for the State Route 400 Express Lanes Project

View this email in your browser
For Immediate Release
Friday, September 26, 2025
Contact:
Lane Closure Advisory for the State Route 400
Express Lanes Project
The project will construct new express lanes in both directions along an approximately 16-mile section of State Route (SR) 400 from the Metropolitan Atlanta Rapid Transit Authority (MARTA) North Springs Station (Exit 5C) in Fulton County to approximately 1 mile north of McFarland Parkway (Exit 12) in Forsyth County.

What: Weather permitting, the Georgia Department of Transportation's contractors will temporarily close traffic lanes at the areas identified below to perform roadwork activities on the SR 400 Express Lanes project.
Lane Closure(s):
Activity Start Date End Date Times
SR 400 Southbound
  • SR 400 SB from SR 141 (MM 27) to Old Milton Parkway (MM 19)
Single, outside right-lane and shoulder closure Sunday, September 28 Friday, October 3 9 p.m. - 5 a.m.
  • SR 400 SB from Old Milton Parkway (MM 19) to Holcomb Bridge Road (MM 15)
Single, outside right-lane and shoulder closure Sunday, September 28 Friday, October 3 9 p.m. - 5 a.m.
  • SR 400 SB from Holcomb Bridge Road (MM 15) to Abernathy Road (MM 8)
Single, outside right-lane and shoulder closure Sunday, September 28 Friday, October 3 9 p.m. - 5 a.m.
  • SR 400 SB from SR 141 (MM 27) to Old Milton Parkway (MM 19)
Double, inside left-lane and shoulder closure Sunday, September 28 Friday, October 3 9 p.m. - 5 a.m.
  • SR 400 SB from Old Milton Parkway (MM 19) to Holcomb Bridge Road (MM 15)
Double, inside left-lane and shoulder closure Sunday, September 28 Friday, October 3 9 p.m. - 5 a.m.
  • SR 400 SB from Holcomb Bridge Road (MM 15) to Abernathy Road (MM 8)
Double, inside left-lane and shoulder closure Sunday, September 28 Friday, October 3 9 p.m. - 5 a.m.
  • SR 400 SB from McFarland Pkwy to McGinnis Ferry Rd
Shoulder closure Monday, September 29 Friday, October 3 7 a.m. - 5 p.m.
SR 400 Northbound
  • SR 400 NB from Abernathy Road (MM 8) to Holcomb Bridge Road (MM 15)
Single, outside right-lane and shoulder closure Sunday, September 28 Friday, October 3 9 p.m. - 5 a.m.
  • SR 400 NB from Holcomb Bridge Road (MM 15) to Old Milton Parkway (MM 19)
Single, outside right-lane and shoulder closure Sunday, September 28 Friday, October 3 9 p.m. - 5 a.m.
  • SR 400 NB from Old Milton Parkway (MM 19) to SR 141 (MM 27)
Single, outside right-lane and shoulder closure Sunday, September 28 Friday, October 3 9 p.m. - 5 a.m.
  • SR 400 NB from Abernathy Road (MM 8) to Holcomb Bridge Road (MM 15)
Double, inside left-lane and shoulder closure Sunday, September 28 Friday, October 3 9 p.m. - 5 a.m.
  • SR 400 NB from Holcomb Bridge Road (MM 15) to Old Milton Parkway (MM 19)
Double, inside left-lane and shoulder closure Sunday, September 28 Friday, October 3 9 p.m. - 5 a.m.
  • SR 400 NB from Old Milton Parkway (MM 19) to SR 141 (MM 27)
Double, inside left-lane and shoulder closure Sunday, September 28 Friday, October 3 9 p.m. - 5 a.m.
  • SR 400 NB from McGinnis Ferry Rd to McFarland Pkwy
Shoulder closure Monday, September 29 Friday, October 3 7 a.m. - 5 p.m.
Other Locations
  • Old Milton Pkwy SB
Inside, Left Lane Ramp Closure Sunday, September 28 Friday, October 3 9 p.m. - 5 a.m.
  • Northridge NB Exit
Inside, Left Lane Ramp Closure
Sunday, September 28 Friday, October 3
9 p.m. - 5 a.m.
  • Spalding Dr
Single, Left or Right Lane Closure
Sunday, September 28 Friday, October 3 9 p.m. - 5 a.m.
  • Westside Pkwy
Single, Left or Right Lane Closure
Sunday, September 28 Friday, October 3 9 p.m. - 5 a.m.
  • Morris Rd
Single, Left or Right Lane Closure
Sunday, September 28 Friday, October 3 9 p.m. - 5 a.m.
  • MARTA NB Entrance
Outside, Right Lane Ramp Closure Sunday, September 28 Friday, October 3 9 p.m. - 5 a.m.
  • Holcomb Bridge Road SR 400 NB Exit Ramp and Holcomb Bridge Road WB from SR 400 to Dogwood Rd
Single, Right Lane Closure
Sunday, September 28 Friday, October 3 9 p.m. - 5 a.m.
  • McFarland Pkwy SB Exit
Outside, Right Lane Ramp Closure Sunday, September 28 Friday, October 3 9 p.m. - 5 a.m.
  • Holcomb Br Rd EB
Single, Left Lane Closure Sunday, September 28 Friday, October 3
9 p.m. - 5 a.m.
  • Holcomb Bridge Rd NB Exit
Outside, Right Lane Ramp Closure Sunday, September 28 Friday, October 3 9 p.m. - 5 a.m.
  • Northridge SB Exit
Outside, Right Lane Ramp Closure Sunday, September 28 Friday, October 3 9 p.m. - 5 a.m.
  • Northridge SB Entrance
Inside, Left Lane Ramp Closure Sunday, September 28 Friday, October 3 9 p.m. - 5 a.m.
  • Holcomb Br Rd WB
Single, Left Lane Closure Sunday, September 28 Friday, October 3 9 p.m. - 5 a.m.
  • Abernathy Rd SB Exit
Single, Left or Right Lane Closure
Sunday, September 28 Friday, October 3 9 p.m. - 5 a.m.
  • McFarland Pkwy NB Exit 12
Single, Right Lane Closure
Sunday, September 28 Friday, October 3
9 p.m. - 5 a.m.
Advisory: Motorists are advised to expect delays, exercise caution, and reduce their speed while traveling through work zones. Work schedule updates can occur, so check the SR 400 Express Lanes website for the latest updates. Additionally, before heading out, get real-time information on work status and traffic conditions by calling " 511," visiting 511ga.org, or downloading the "Georgia 511" app.
Follow Us
Like Us
Visit Us
See Us
Watch Us
The information you provide to the Georgia Department of Transportation will be used solely by GDOT. The Department does not sell or offer a subscriber's personal information to third parties for marketing purposes. To no longer receive this e-news letter, please select "unsubscribe from this list" below.
Copyright © 2025 Georgia Department of Transportation, All rights reserved.

Our mailing address is:
Georgia Department of Transportation
Office of Communications
600 West Peachtree Street N.W.
Atlanta, GA 30308

Want to change how you receive these emails?
You can update your preferences or unsubscribe from this list
Georgia Department of Transportation published this content on September 26, 2025, and is solely responsible for the information contained herein. Distributed via Public Technologies (PUBT), unedited and unaltered, on September 27, 2025 at 15:31 UTC. If you believe the information included in the content is inaccurate or outdated and requires editing or removal, please contact us at [email protected]