New traffic signals activated at N Rosa Parks Way & Greeley Avenue as project nears completion

Label: News article
Work starts next week to rebuild corners, followed by paving repair and final striping.
Published
July 9, 2026 9:40 am

Portland Bureau of Transportation (PBOT) crews have installed and activated new traffic signals as part of the N Rosa Parks Way & Greeley Avenue Crossing & Signal Project.

Starting next week, our contractor will begin final steps to complete the project. They will rebuild corner ramps, driveway approaches, and sidewalk near the intersection. They will work on one corner at a time starting at the northeast corner. Each corner will take approximately one week to complete.

Following the concrete work, our contractor will repair pavement and install final striping. All work should be complete in the next one to two months.

Pedestrians should expect detours around the work areas. People driving and biking should travel cautiously through the work zone. Transit users should check TriMet for impacts on nearby bus stops.

Thank you for your patience as we near completion on this project.

City of Portland, OR published this content on July 09, 2026, and is solely responsible for the information contained herein. Distributed via Public Technologies (PUBT), unedited and unaltered, on July 09, 2026 at 17:14 UTC. If you believe the information included in the content is inaccurate or outdated and requires editing or removal, please contact us at [email protected]