11/12/2026 | Press release | Archived content
In many cases, developers have made explicit financial commitments to host communities. One of the largest as of October 2026 is NorthPoint Development's proposed $165 million package for Project Hazelnut in Hazle Township, Pennsylvania: $45 million in $10,000 grants to every eligible household, $15 million for workforce and education initiatives, and $105 million to the township over 15 years.⁷
Other agreements have been smaller and more targeted: $20 million in Lancaster, Pennsylvania, tied to clean energy use, local hiring and annual transparency reporting; $15 million for citywide Wi-Fi in St. Louis, Missouri; $15 million for an animal shelter in Ellis County, Texas; and $10 million toward a recreation center in Saline, Michigan, agreed after litigation.⁸
The scale of these financial packages varies widely, yet communities and developers often lack a robust analytical framework to benchmark them. The ICE Construction Disruption Model can deliver this framework by providing transparent expected delay costs for both developers and local communities.
Data Center Tracker⁵ records of 1,486 legislative actions show that the median affected project involves $2.7 billion in capital expenditure. Aswath Damodaran of New York University estimated the January 2026 cost of capital for real-estate development at 5.82%, and 6.96% for the total U.S. market,⁹ while project-level construction financing sits above both. At a carrying cost of 6%-10% on committed capital, a 12-month delay on a $2.7 billion project costs between $162 million to $270 million. This range can be weighted by probability of disruption.
Figure 2 illustrates how expected carrying costs scale with disruption probability for a $2.7 billion project. A developer facing a 30% probability of disruption on a median-sized project carries $49 million to $81 million of expected carrying cost before any commitment is discussed, comparable to the Lancaster, St. Louis and Ellis County agreements combined.