11/24/2026 | Press release | Distributed by Public on 11/24/2026 08:04
Fast facts:
COLOMA, Mich. - The Michigan Department of Transportation (MDOT) and contractor Kalin Construction Co. Inc. on Wednesday, Nov. 25, are expecting to reopen M-139 between I-94 Business Loop (BL) (Main Street) in Benton Harbor and Pipestone Road in Benton Charter Township, marking the completion of the first year of a two-year, $24.4 million investment involving culvert construction and drainage improvements, sidewalk upgrades, signal modernization and municipal utilities.
This year, crews completed rebuilding M-139 north of Pipestone Road, including building a roundabout at Empire Avenue, box culvert installation and a two-way street conversion. In addition to the M-139 work, Fair Avenue was rebuilt from Empire Avenue to I-94 BL, including new watermain, sanitary sewer, storm sewer, curb, sidewalk upgrades and a two-way conversion. Fair Avenue work also included box culvert installation, which will be wrapping up prior to the pause for the winter.
During the winter pause, northbound M-139 will have one lane closed from Pipestone Road to Empire Avenue to establish the new lane configuration leading into the roundabout.
Work is expected to resume in April 2027 to complete construction from Pipestone Road to north of the St. Joseph River.
Closure and detour information is available on Mi Drive; updates will be shared ahead of construction phase changes.
Based on economic modeling, this $24.4 million investment is expected to directly and indirectly support 206 jobs.