The 2025 Road Repair Project will bring preventative maintenance to a variety of locations throughout the City.
Work will consist of the following:
Milling and repaving
Harkins Slough Road from Green Valley Road to Struve Slough Bridge
Loma Prieta Avenue from Green Valley Road to Airport Boulevard
Kilburn Street from Ford Street to West 5th Street
Slurry Seal (surface treatment)
Harkins Slough Road from Ohlone Parkway to Blackbird Circle
Green Valley Road from Main Street to Carey Avenue
Freedom Boulevard from Alta Vista Avenue to Main Street
Ford Street from Rodriguez Street to Walker Street
Schedule
Construction will begin Monday, October 13th, and is expected to last 1-2 weeks depending on weather. Work will be done Monday-Friday 7:00AM-6:00Pm.
Funding
Funding for this project comes from the Road Repair and Accountability Act (SB1) and Measure D.