Crews will resurface roughly 200,000 square yards of Terra Linda roadway to extend pavement life and smooth local streets.

Improvements are coming to streets throughout the Terra Linda neighborhood. Construction on the 2025/2026 Pavement Maintenance Project starts Thursday, August 20, 2026, and is expected to run through early September 2026.

The project will apply a slurry seal treatment to about 200,000 square yards of roadway. Slurry seal is a protective coating that fills small cracks and renews the road surface, helping streets last longer and stay smoother.

Once complete, the project will improve pavement conditions across dozens of Terra Linda streets and extend the life of the roads before more costly repairs are needed.

What to expect during construction

Work runs on weekdays over two phases. Crack seal work is scheduled for August 20, 21, 24, 26, and 28. Slurry seal work follows on August 25 through September 4. Dates are subject to change due to weather.

During the work, designated streets will be partially or fully closed, and there will be no parking on streets scheduled for treatment that day. Please move vehicles off the street before your block's scheduled date. Some blocks are closed by side ("even" or "odd" addresses) or in the morning versus afternoon, so watch for posted signs on your street.

Access to homes will be maintained whenever possible. The City will provide advance notice of significant access changes through project webpage updates and social media.

Traffic control and detours

Most affected streets are residential. Some will be fully closed for the day, while busier streets like Montecillo Road, Nova Albion Way, and Golden Hinde Boulevard will stay open with lane restrictions and flaggers directing traffic.

Drivers should allow extra time and use alternate routes when possible. Detour signs and traffic-control personnel will guide travelers through or around work areas. Follow all posted no-parking and closure signs.

Stay informed

The City appreciates the community's patience and cooperation while this work is completed. Construction schedules are subject to change due to weather, site conditions, or other unexpected circumstances. Learn more by visiting the Pavement Maintenance Project webpage.

Full schedule

Crack seal:

Thursday 8/20
Street From To
Bamboo Terrace Las Ovejas Ave Montecillo Road
Birchwood Court Butternut Drive End
Butternut Drive Mahogany Drive End
Fowler Court De Ford Drive End
Le Claire Ct Nova Albion Way End
Mahogany Drive Butternut Drive End
Montecillo Dr Tarragon Dr De Ford Drive
Montecillo Dr Trellis Dr Tamarack Dr
Montecillo Dr Nova Albion Way Trellis Dr
Tamarrack Dr Montecillo Dr Devon Drive
Terra Linda Dr Esmeyer Dr End
Wellbrock Heights Trellis Dr End
Friday 8/21
Street From To
Ana Ct Elena Cir End
Arias St Trellis Dr Elena Cir
Barberry Lane Bamboo Terrace Bamboo Terrace
Butternut Drive Mahogany Drive Montecillo Road
Caroll Ct Lenglen Ave End
De Ford Drive Fowler Court Montecillo Road
Elda Dr Esmeyer Dr Regina Way
Elena Cir Arias St Ana Ct
Fowler Court Lea Drive De Ford Drive
Lea Drive Fowler Court Esmeyer Drive
Lenglen Ave Tamarack Dr Trellis Dr
Luisa Ct Elena Cir End
Minor Ct Tamarack Dr End
Regina Way Santa Clara Ct Elda Dr
San Mateo Ct Lea Dr End
Sandalwood Ct Manuel T Freitas Pkwy End
Santa Clara Ct Regina Way End
Tanbark Terr Thornwood Terrace Tamarack Dr
Wallace Way Tamarack Dr Devon Dr
Monday 8/24
Street From To
Arcangel Way Del Haro way De Anza Way
Ayala Ct Arcangel Way End
Billou St Bret Ave Dui Bois St
Cemenho Ct Nova Albion Way End
Corte Pacheco Nova Albion Way End
De Anza Way Golden Hinde Blvd End
Del Haro Way Golden Hinde Blvd End
Denning Way Tamarack Dr End
Don Timoteo Ct Nova Albion Way End
Drakes Cove Golden Hinde Blvd End
El Pavo Real Cir Nova Albion Way Nova Albion Way
Elda Drive Regina Way Tamarack Drive
Esmeyer Dr Tamarack Dr Nova Albion Way
Estero Way Nova Albion Way End
Lea Drive Fowler Court Esmeyer Drive
Nova Albion Way Montecillo Road Las Gallinas Ave
Regina Way Santa Clara Ct Elda Drive
Sao Augustine Way Nova Albion Way End
Sussex Ct Golden Hinde Blvd End
Viscaino Way Nova Albion Way End
Weddnesday 8/26
Street From To
Esmeyer Dr Elda Dr End
Golden Hinde Blvd Nova Albion Way Los Ranchitos Rd
Trellis Dr Arias St Montecillo Road
Friday 8/28
Street From To
Nova Albion Way Montecillo Road Northgate Drive

Slurry seal:

Tuesday, August 25, 2026
Street From To Side of Street that will be closed
Sandalwood Ct Manuel T Freitas Pkwy End Full Closure
San Mateo Ct Lea Dr End Full Closure
Fowler Court De Ford Drive End Full Closure
Montecillo Dr Tarragon Dr De Ford Drive W Lane Lane
Tanbark Terr Thornwood Terrace Tamarack Dr Even A.M.
Tanbark Terr Thornwood Terrace Tamarack Dr Odd P.M.
Terra Linda Dr Esmeyer Dr End Full Closure
Santa Clara Ct Regina Way End Full Closure
Elda Ct Tamarack Dr End Full Closure
Caroll Ct Lenglen Ave End Full Closure
Wellbrock Heights Trellis Dr End Full Closure
Elda Dr Esmeyer Dr Regina Way Full Closure Even
Luisa Ct Elena Cir End Full Closure
Wednesday, August 26, 2026
Street From To Side of Street that will be closed
Butternut Drive Mahogany Drive End Full Closure
Mahogany Drive Butternut Drive End Full Closure
Birchwood Court Butternut Drive End Full Closure
Bamboo Terrace Las Ovejas Ave Barberry Lane Even A.M.
Bamboo Terrace Las Ovejas Ave Barberry Lane Odd P.M.
Montecillo Dr Tarragon Dr De Ford Drive E Lane Lane
Lea Drive Manuel T Freitas Pkwy Fowler Court Even A.M.
Lea Drive Manuel T Freitas Pkwy Fowler Court Odd P.M.
Elda Dr Esmeyer Dr Regina Way Full Closure Odd
Ana Ct Elena Cir End Full Closure
Thursday, August 27, 2026
Street From To Side of Street that will be closed
Butternut Drive Mahogany Drive Montecillo Road Even/Split - Flaggers
Bamboo Terrace Barberry Lane Montecillo Road Even A.M.
Bamboo Terrace Barberry Lane Montecillo Road Odd P.M.
Montecillo Dr Tarragon Dr De Ford Drive Center Lane Lane
Elena Cir Arias St Ana Ct Even
Minor Ct Tamarack Dr End Full Closure
Denning Way Tamarack Dr End Full Closure
Le Claire Ct Nova Albion Way End Full Closure
El Pavo Real Cir Nova Albion Way Nova Albion Way Full Closure Even
Corte Pacheco Nova Albion Way End Full Closure
Cemenho Ct Nova Albion Way End Full Closure
Don Timoteo Ct Nova Albion Way End Full Closure
Montecillo Dr Nova Albion Way Trellis Dr N Lane Lane
Montecillo Dr Trellis Dr Tamarack Dr N Lane Lane
Friday, August 28, 2026
Street From To Side of Street that will be closed
Butternut Drive Mahogany Drive Montecillo Road Odd/Split -Flaggers
Barberry Lane Bamboo Terrace Bamboo Terrace Even A.M.
Barberry Lane Bamboo Terrace Bamboo Terrace Odd P.M.
Regina Way Lea Drive Elda Dr Even A.M.
Regina Way Lea Drive Elda Dr Odd P.M.
Elda Dr Tamarack Dr Regina Way Even A.M.
Elda Dr Tamarack Dr Regina Way Odd P.M.
Elena Cir Arias St Ana Ct Odd
El Pavo Real Cir Nova Albion Way Nova Albion Way Full Closure Odd
Esmeyer Dr Lea Dr End Full Closure
Viscaino Way Nova Albion Way End Full Closure
Estero Way Nova Albion Way End Full Closure
Sao Augustine Way Nova Albion Way End Full Closure
Del Haro Way Arcangel Way End Full Closure
De Anza Way Arcangel Way End Full Closure
Sussex Ct Golden Hinde Blvd End Full Closure
Drakes Cove Golden Hinde Blvd End Full Closure
Ayala Ct Arcangel Way End Full Closure
Monday, August 31, 2026
Street From To Side of Street that will be closed
Tamarrack Dr Montecillo Dr Esmeyer Drive Even
Montecillo Dr Nova Albion Way Trellis Dr 46025 S Lane
Montecillo Dr Trellis Dr Tamarack Dr 46025 S Lane
Nova Albion Way Esmeyer Dr Las Gallinas Ave Even
Golden Hinde Blvd Nova Albion Way Los Ranchitos Rd Even A.M.
Golden Hinde Blvd Nova Albion Way Los Ranchitos Rd Odd P.M.
Fowler Court Lea Drive De Ford Drive Even
De Ford Drive Fowler Court Montecillo Road Even
Tuesday, , September 1, 2026
Street From To Side of Street that will be closed
Nova Albion Way Esmeyer Drive Northgate Dr Even ( Bell
Billou St Bret Ave Dui Bois St Full Closure
Tamarrack Dr Montecillo Dr Esmeyer Drive Odd
Fowler Court Lea Drive De Ford Drive Odd
De Ford Drive Fowler Court Montecillo Road Odd
Montecillo Dr Trellis Dr Tamarack Dr N Lane A.M.
Montecillo Dr Trellis Dr Tamarack Dr Center Lane P.M.
Montecillo Dr Nova Albion Way Trellis Dr N Lane A.M.
Montecillo Dr Nova Albion Way Trellis Dr Center Lane P.M.
Arias St Trellis Dr Elena Cir Even A.M.
Arias St Trellis Dr Elena Cir Odd P.M.
Wednesday, September 2, 2026
Street From To Side of Street that will be closed
Nova Albion Way Esmeyer Dr Las Gallinas Ave Odd
Lea Drive Fowler Court Esmeyer Drive Even A.M.
Lea Drive Fowler Court Esmeyer Drive Odd P.M.
Del Haro Way, Arcangel Way, De Anza Way Loop Golden Hinde Blvd Golden Hinde Blvd Even A.M.
Del Haro Way, Arcangel Way, De Anza Way Loop Golden Hinde Blvd Golden Hinde Blvd Odd P.M.
Tamarack Dr Esmeyer Dr Devon Dr Even A.M.
Tamarack Dr Esmeyer Dr Devon Dr Odd P.M.
Trellis Dr Arias St Montecillo Road Even
Thursday, September 3, 2026
Street From To Side of Street that will be closed
Nova Albion Way Esmeyer Drive Northgate Dr Odd
Esmeyer Dr Lea Dr Elda Dr Even AM
Esmeyer Dr Lea Dr Elda Dr Odd P.M.
Wallace Way Tamarack Dr Devon Dr Even AM
Wallace Way Tamarack Dr Devon Dr Odd P.M.
Lenglen Ave Tamarack Dr Trellis Dr Even AM
Lenglen Ave Tamarack Dr Trellis Dr Odd P.M.
Esmeyer Dr Tamarack Dr Nova Albion Way Even AM
Esmeyer Dr Tamarack Dr Nova Albion Way Odd P.M.
Trellis Dr Arias St Montecillo Road Odd
Friday, September 4 , 2026
Street From To Side of Street that will be closed
Trellis Dr Montecillo Dr Esmeyer Drive Even AM
Trellis Dr Montecillo Dr Esmeyer Drive Odd P.M.
City of San Rafael, CA published this content on August 19, 2026, and is solely responsible for the information contained herein. Distributed via Public Technologies (PUBT), unedited and unaltered, on August 19, 2026 at 22:51 UTC. If you believe the information included in the content is inaccurate or outdated and requires editing or removal, please contact us at [email protected]