Traffic Impacts Related to The I-285/I-20 West Interchange Project
|
|
This project will reconstruct and widen several interstate, system-to-system ramps at the I-285/I-20 West Interchange and add a combination of collector-distributor (CD) lanes or connecting lanes and auxiliary lanes along I-20 west and I-285 north of the interchange.
What: Weather permitting, the Georgia Department of Transportation (Georgia DOT) contractors will temporarily close traffic lanes at the areas identified below to perform roadwork activities on the I-285/I-20 West Interchange project.
Note: Detour information is shown in red text.
|
|
Lane Closure(s):
Roadway
|
Activity
|
Start Date
|
End Date
|
Times
|
I-285 Northbound
|
Cascade Road to Bolton Road
|
Single, right-lane, and right-shoulder closure
|
Monday, September 15
|
Saturday, September 20
|
9 p.m. - 5 a.m. Nightly
|
Cascade Road to Bolton Road
|
Double, right-lane, and right-shoulder closure
|
Monday, September 15
|
Saturday, September 20
|
11 p.m.- 5 a.m.
Nightly
|
I-285 Southbound
|
SR 280/South Cobb Drive to I-20 Interchange
|
Pacing operation, all lanes and shoulders
|
Monday, September 15
|
Thursday, September 18
|
10:30 a.m.-12 p.m. Daily
|
US 78/Donald Lee Hollowell Pkwy to SR 139/MLK Jr. Drive
|
Single, right-lane, and right-shoulder closure
|
Monday, September 15
|
Saturday, September 20
|
9 p.m. - 5 a.m. Nightly
|
I-20 Westbound
|
Anderson Avenue underpass to Riverside Parkway
|
Single, right-lane, and right-shoulder closure
|
Monday, September 15
|
Saturday, September 20
|
9 p.m. - 5 a.m. Nightly
|
I-20 Eastbound
|
Riverside Parkway to the I-285 Interchange
|
Alternating, single, right-lane, and right-shoulder, and single, left-lane, and left-shoulder closure
|
Monday, September 15
|
Saturday, September 20
|
9 p.m. - 5 a.m.
Nightly
|
Other Locations
|
SR 70/Fulton Industrial Boulevard SB from Wendell Drive to Shirley Drive
|
Single, right-lane, and right-shoulder closure
|
Monday, September 15
|
Saturday, September 20
|
8 p.m. - 5 a.m.
Nightly
|
SR 139/MLK Jr. Drive NB from Old Gordon Road to Adamsville Drive
|
Single, right-lane, and right-shoulder closure
|
Monday, September 15
|
Saturday, September 20
|
8 p.m. - 5 a.m.
Nightly
|
ADVANCE NOTICE & DETOURS
|
I-285 Southbound to I-20 Eastbound ramp closure
|
Overnight closure and detour (Map)
Motorists traveling on I-285 southbound will continue south to SR 139/Martin Luther King Jr. Drive (Exit 9) to I-285 northbound and merge onto I-20 eastbound.
|
Friday, September 26
|
Friday, October 3
|
9 p.m. until 5 a.m.
Nightly
|
|
|
|
Advisory: Motorists are advised to expect delays, exercise caution, reduce their speed while traveling through work zones, stay alert, and watch for workers. Before heading out, get real-time information on work status and traffic conditions. Call 511, visit 511ga.org, or download the Georgia 511 app.
|
|
|