City of Bloomington, IL

08/10/2026 | Press release | Distributed by Public on 08/10/2026 14:51

Resurfacing Update: August 10, 2026

BLOOMINGTON, IL - The City of Bloomington provides regular updates on resurfacing work throughout the construction season. The most recent update is included below.

For more information on roadwork in the City of Bloomington, visit www.bloomingtonstreets.com, e-mail [email protected] or call 309-434-2980 during regular business hours. Residents can also sign up for e-mail or text updates for Bloomington Streets by visiting www.bloomingtonil.gov/subscribe and subscribing to Bloomington Streets.

FY26 Resurfacing

E. Oakland Ave, west of Prospect through Hershey

  • A final inspection has been completed and clean-up will be scheduled

Prospect Rd, Oakland to Empire

  • A final inspection has been completed and clean-up will be scheduled

E. Washington St, Veterans through Hershey

  • A final inspection has been completed and clean-up will be scheduled

FY27 Resurfacing

Eastland Dr, Fairway to Hershey

Stage 1: Veterans to Hershey

  • Installation of the asphalt surface course has been completed
  • Replacement of the underground utility castings (manholes and water valves) has been completed
  • Installation of the pavement striping has been tentatively scheduled

Stage 2: Fairway to Veterans

  • Removal and replacement of the underground utility work has been completed
  • Removal and replacement of the concrete items (curb and gutter, sidewalks, and ramps) is in progress
  • Removal of the underground utility castings has been scheduled
  • Removal (milling) of the concrete and asphalt surfaces has been scheduled for the week of August 10

Four Seasons Rd, north of Oakland through the cul-de-sac

  • Removal and replacement of the concrete items (curb and gutter, sidewalks, and ramps) has been completed
  • Removal (milling) of the concrete surface has been completed
  • Installation of the sand binder course has been completed
  • Installation of the asphalt surface course has been completed
  • Replacement of the underground utility castings (manholes and water valves) is in progress
  • Installation of the asphalt surface at the intersections has been scheduled for the week of August 10
  • Installation of the pavement striping has been tentatively scheduled

St. Joseph Dr, Washington to Eastland

  • Installation of the pavement striping has been tentatively scheduled

Contact:
Katherine Murphy
Communications & External Affairs Mgr.
Phone: 309-434-2241
Email: [email protected]

Contact:
Jim Karch
Director of Engineering
Phone: 309-434-2980
E-mail: [email protected]

City of Bloomington, IL published this content on August 10, 2026, and is solely responsible for the information contained herein. Distributed via Public Technologies (PUBT), unedited and unaltered, on August 10, 2026 at 20:51 UTC. If you believe the information included in the content is inaccurate or outdated and requires editing or removal, please contact us at [email protected]