BART - San Francisco Bay Area Rapid Transit District

05/21/2026 | Press release | Distributed by Public on 05/21/2026 11:01

Single Tracking Alert: Service reduced to only one track in the Transbay Tube on three Sundays for critical lighting work (next work date 6/7)

Single Tracking Alert: Service reduced to only one track in the Transbay Tube on three Sundays for critical lighting work (next workday Sunday, June 7)

BART crews will be in the Transbay Tube to replace lights in the tube on three upcoming Sundays. The work will take place on June 7, and July 19.

The work will be for the entire day on all three Sundays, which will reduce our normal service from two tracks to one. Service impacts on both days will include:

  • Trains will run every 30 minutes systemwide
  • Only 3 lines will be in service (Blue, Yellow, Orange)
  • Red and Green Line service will not operate
  • A Yellow Line shuttle train will run between SFO and Millbrae all day - Passengers traveling beyond SFO must transfer

BART's Trip Planner will be updated to reflect schedule changes for these days. Riders are strongly encouraged to plan their trips in advance.

(This article was originally published on 3/30/26.)

BART - San Francisco Bay Area Rapid Transit District published this content on May 21, 2026, and is solely responsible for the information contained herein. Distributed via Public Technologies (PUBT), unedited and unaltered, on May 21, 2026 at 17:01 UTC. If you believe the information included in the content is inaccurate or outdated and requires editing or removal, please contact us at [email protected]