Construction Update: Telfair Street and Greene Street

AUGUSTA - RICHMOND COUNTY GOVERNMENT

Communications

-------------------------------------------------------------------

AUGUSTA, GA - Construction Update: Telfair Street and Greene Street

AUGUSTA, GA (October 17, 2025) - Progress on the Broad Street Improvement Project is continuing with the following upcoming work scheduled:

· Telfair Street (7th Street intersection to 6th Street) - This section of Telfair Street is closed for traffic while crews complete construction activities including drainage improvement work. Work is expected to be completed within three to four weeks. Please plan alternate routes and allow extra travel time. We'll share updates if the closure needs to remain in place longer.

· Greene Street (3rd Street to East Boundary) - Weather permitting, paving is scheduled to take place on Saturday, October 25. Irrigation installation is currently underway in this area.

For more information, please contact Augusta Engineering & Environmental Services Department: [email protected].


# # #

You are subscribed to Augusta Announcements

Connect with AUG GOV:

Facebook | X (Twitter) | Instagram | LinkedIn | City Website | YouTube

Augusta - Richmond County Government

City of Augusta and Richmond County, GA published this content on October 17, 2025, and is solely responsible for the information contained herein. Distributed via Public Technologies (PUBT), unedited and unaltered, on October 17, 2025 at 20:01 UTC. If you believe the information included in the content is inaccurate or outdated and requires editing or removal, please contact us at [email protected]