Report looks at reasons for Vogtle construction delays

A lack of a realistic schedule; a failure to adhere to the Nuclear Regulatory Commission's quality assurance requirements; and changes to Westinghouse's AP1000 incomplete reactor design during construction were the primary reasons Vogtle-3 and -4 suffered delays, a new report says.

Columbia University's Center on Global Energy Policy (CGEP) issued its report, "Insights into Construction Delays at the Vogtle Nuclear Plant: Primary Sources of Delay Identified by the Independent Construction Monitor," on November 15. This report investigated the delays that ultimately made the country's most recent commercial reactor project a costly affair and outlined the lessons learned that current and future projects can take from Vogtle.

What caused the delays: Report authors Matt Bowen and Rama Ponangi dug into the yearslong testimony of William Jacobs Jr., the project's independent construction monitor (ICM). As part of the Vogtle project, Georgia Power was required to hire an ICM to assist the Georgia Public Service Commission in monitoring the project. Jacobs submitted testimony from 2009 through 2023 as part of the project's semiannual reports. Bowen and Ponangi said they combed through roughly 1,200 pages of Jacobs's written testimony as well as associated Vogtle construction monitoring reports.

"While the ICM could not be expected to know everything about such a large project, was testifying in real time as the project unfolded, and early on said he was not given adequate access to project documents-as well as the fact that substantial portions of the ICM testimonies have been redacted-Jacobs's collective testimonies help illuminate the challenges that the Vogtle 3 and 4 reactors encountered on their way to commercial operation," they wrote.

The report listed three primary reasons for the delays at Vogtle-3 and -4, which entered commercial operation in 2023 and 2024, respectively:

  • The project lacked a realistic and achievable integrated project schedule (IPS). The authors argued that an IPS is necessary for megaprojects, because it "integrates the potentially hundreds of thousands of activities that have to be accomplished by thousands of workers over thousands of days into a logically tied, sequence-dependent manner." The first time the ICM scrutinized the schedule was in a 2012 testimony, and the concerns continued through the ICM's final report.
  • The project did not adhere to the NRC's stringent quality assurance requirements. According to the authors' investigations, the ICM found that those who signed the engineering, procurement, and construction agreement in 2008 were not prepared initially to meet those requirements and "develop, implement, and execute a 10 CFR 50 Appendix B quality assurance program and that the lack of preparedness impacted the project for years." Of particular concern was a Louisiana facility with no prior nuclear-grade manufacturing experience that "created lasting problems," the report said.
  • Westinghouse lacked sufficient design completion when the project began, and the design changed during construction. Parts of the AP1000 design were not complete at the start of construction, and the ICM said one of the first lessons to take from this project was that "the design of the project should be well advanced prior to initiation of construction activities." For example, only 40 percent of the AP1000 plant engineering documents were issued when the project received its combined construction and operating license from the NRC in 2012. The incomplete and changing design resulted in issues with the licensing process.

The CGEP report listed a few other reasons for the delays. These included a failure to meet productivity targets and to improve productivity, a failure to stay in the bulk construction mode before starting commissioning activities, extensive use of the partial release for test (PRT) process, and a failure to prioritize completion of planned work in the most efficient sequence possible.

Lessons learned: Along with the importance of a mature design, the report identified two other lessons learned from the ICM's testimony on the Vogtle delays:

  • A complete Level 3 integrated project schedule with "realistic, achievable inputs" should be required.
  • Strong quality-control measures early in the construction process should be required, and suppliers with prior nuclear-grade manufacturing experience should be used.

"The calamitous experience of the Vogtle 3 and 4 project will need to be avoided in the future if new reactors are to become a growing part of the U.S. energy mix," the report concluded. "Getting a nuclear plant built cost-effectively and on time will be especially consequential as reactors compete with alternative energy sources in varying policy and public acceptance environments in the United States."

ANS - American Nuclear Society published this content on November 25, 2026, and is solely responsible for the information contained herein. Distributed via Public Technologies (PUBT), unedited and unaltered, on November 25, 2026 at 15:32 UTC. If you believe the information included in the content is inaccurate or outdated and requires editing or removal, please contact us at [email protected]