11/25/2026 | News release | Distributed by Public on 11/25/2026 09:32
A lack of a realistic schedule; a failure to adhere to the Nuclear Regulatory Commission's quality assurance requirements; and changes to Westinghouse's AP1000 incomplete reactor design during construction were the primary reasons Vogtle-3 and -4 suffered delays, a new report says.
Columbia University's Center on Global Energy Policy (CGEP) issued its report, "Insights into Construction Delays at the Vogtle Nuclear Plant: Primary Sources of Delay Identified by the Independent Construction Monitor," on November 15. This report investigated the delays that ultimately made the country's most recent commercial reactor project a costly affair and outlined the lessons learned that current and future projects can take from Vogtle.
What caused the delays: Report authors Matt Bowen and Rama Ponangi dug into the yearslong testimony of William Jacobs Jr., the project's independent construction monitor (ICM). As part of the Vogtle project, Georgia Power was required to hire an ICM to assist the Georgia Public Service Commission in monitoring the project. Jacobs submitted testimony from 2009 through 2023 as part of the project's semiannual reports. Bowen and Ponangi said they combed through roughly 1,200 pages of Jacobs's written testimony as well as associated Vogtle construction monitoring reports.
"While the ICM could not be expected to know everything about such a large project, was testifying in real time as the project unfolded, and early on said he was not given adequate access to project documents-as well as the fact that substantial portions of the ICM testimonies have been redacted-Jacobs's collective testimonies help illuminate the challenges that the Vogtle 3 and 4 reactors encountered on their way to commercial operation," they wrote.
The report listed three primary reasons for the delays at Vogtle-3 and -4, which entered commercial operation in 2023 and 2024, respectively:
The CGEP report listed a few other reasons for the delays. These included a failure to meet productivity targets and to improve productivity, a failure to stay in the bulk construction mode before starting commissioning activities, extensive use of the partial release for test (PRT) process, and a failure to prioritize completion of planned work in the most efficient sequence possible.
Lessons learned: Along with the importance of a mature design, the report identified two other lessons learned from the ICM's testimony on the Vogtle delays:
"The calamitous experience of the Vogtle 3 and 4 project will need to be avoided in the future if new reactors are to become a growing part of the U.S. energy mix," the report concluded. "Getting a nuclear plant built cost-effectively and on time will be especially consequential as reactors compete with alternative energy sources in varying policy and public acceptance environments in the United States."