W. Club Boulevard Corridor Utility Rehabilitation Project Two-Week Look Ahead
September 19, 2025
The City appreciates your ongoing patience with the work associated with this project. Additional information regarding this project can be found at: www.durhamnc.gov/3705.
The contractor, Moffat Pipe, Inc., will perform tie ins to E.K. Powe Elementary School and another 9th Street business on Saturday, September 20. This work will take place on 9th Street from 7 a.m. to 5:30 p.m. The school requested the tie in work be completed during the weekend.
It is anticipated that work on 9th Street between Safeway and W. Knox streets will finish up September 23 and the road will reopen.
Road closure information
Active temporary road closures remain in place on W. Club Boulevard between Alabama Avenue and Maryland Avenue and on 9th Street between Safeway and W. Knox streets.
Project contacts:
Wade Tong, Construction Team Manager, City of Durham, [email protected]
Zeke Urias, Project Manager, Moffat Pipe Inc., [email protected]