MoDOT TRAFFIC ALERT: National Avenue and Broadway Avenue CLOSED under I-44 in S…

Where /When: In Springfield

  • National Avenue CLOSED under I-44
    • Beginning Monday, April 6, until completed
  • Broadway Avenue CLOSED under I-44
    • Beginning Monday, April 6
  • Grant Avenue CLOSED under I-44
    • Crews will move back and forth between Broadway and Grant Avenue, beginning with Broadway Avenue, and will close the road as they work. Message boards will alert drivers to upcoming work zones.

What: Contractor crews are working on the new I-44 bridges over National Avenue, Broadway Avenue, and Grant Avenue. National Avenue will be CLOSED until the work is completed. Broadway and Grant Avenue will be CLOSED intermittently. Crews will move back and forth between Broadway and Grant Avenue, beginning with Broadway Avenue, and will close the road as they work. For example, when Broadway Avenue is closed, Grant Avenue will be open, and when crews close Broadway Avenue, Grant Avenue will be open. This work is part of the Forward 44: Springfield Improvements in Greene County project.

Traffic Impacts:

  • National Avenue under I-44 CLOSED in Springfield
  • Broadway Avenue under I-44 CLOSED intermittently in Springfield
  • Grant Avenue under I-44 CLOSED intermittently in Springfield
  • Drivers will have access to entrances at either end of the work zone, but will not be able to drive through the work zone
  • Detours will be signed. Drivers are urged to find alternate routes.
  • Signs and message boards will alert drivers to work zones and inform the public when there are reduced speeds and traffic delays
  • Check MoDOT's Traveler Information Map for road closures/traffic impacts

Weather and/or construction delays will alter the work schedule .

Project Summary:

  • Widening I-44 to 6 lanes between Missouri Route 13 (Kansas Expressway) and U.S. Route 65
  • Replace the following bridges carrying I-44 over city streets:
    • Broadway Avenue Bridge
    • Grant Avenue Bridge
    • National Avenue Bridge
  • Build a pedestrian underpass and trail improvements east of Grant Avenue
  • Resurface I-44 between west of Missouri Route 266 (Chestnut Expressway) and U.S. Route 160 (West Bypass)
  • Build a sound wall south of I-44 from the National Avenue bridge west, approximately 2,550 feet

Contractor: Capital Paving & Construction LLC, Jefferson City

The awarded construction cost is $70.7 million, including $13.4 million in General Revenue funds provided by the General Assembly and the Governor's Office.

To get project updates or sign up for project emails, visit https://www.modot.org/projects/forward-44-springfield-improvements.

The project is scheduled for completion in May 2027.

END

For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest

Follow MoDOT's Southwest District: Facebook | X | Instagram|YouTube

Take the Challenge! Buckle Up/Phone Down

State of Missouri published this content on April 01, 2026, and is solely responsible for the information contained herein. Distributed via Public Technologies (PUBT), unedited and unaltered, on April 01, 2026 at 19:13 UTC. If you believe the information included in the content is inaccurate or outdated and requires editing or removal, please contact us at [email protected]