Resurfacing Update: October 27, 2025

BLOOMINGTON, IL - The City of Bloomington provides regular updates on resurfacing work throughout the construction season. The most recent update is included below.

For more information on roadwork in the City of Bloomington, visit https://www.bloomingtonstreets.com, e-mail [email protected] or call 309-434-2980 during regular business hours. Residents can also sign up for e-mail or text updates for Bloomington Streets by visiting https://www.bloomingtonil.gov/subscribe and subscribing to Bloomington Streets.

FY25 Resurfacing

G.E. (General Electric) Rd, west of Hershey to Towanda Barnes

Stage 1: (west of Hershey to Airport)

  • Restoration of a driveway approach has been tentatively scheduled

Stage 2: (Airport to Towanda Barnes)

  • Restoration of a driveway approach has been tentatively scheduled

FY26 Resurfacing

E. Oakland Ave, west of Prospect through Hershey

  • Removal and replacement of the storm sewer inlets has been completed
  • Removal and replacement of the concrete items (curb and gutter; ramps) has been completed
  • Removal of the underground utility castings has been completed
  • Removal of the asphalt surface has been completed
  • Installation of the asphalt binder course has been completed
  • Installation of the asphalt surface course shall be completed October 27
  • Restoration of selected driveway approaches has been tentatively scheduled

Prospect Rd, Oakland to Empire

Stage 1: S. Prospect Rd. (Oakland to Washington)

  • Removal and replacement of the storm sewer inlets has been completed
  • Removal and replacement of the concrete items has been completed
  • Removal of the underground utility castings has been completed
  • Removal of the asphalt surface has been completed
  • Installation of the asphalt binder course has been completed
  • Installation of the asphalt surface course has been scheduled for the week of October 27
  • Restoration of selected driveway approaches has been tentatively scheduled

Stage 2: N. Prospect Rd. (Washington to Empire)

  • Removal and replacement of the storm sewer inlets has been completed
  • Removal and replacement of the concrete items (sidewalk; ramps) is in progress
  • Removal of the underground utility castings has been completed
  • Removal of the asphalt surface has been completed
  • Installation of the asphalt binder course has been completed
  • Installation of the asphalt surface course has been scheduled for the week of October 27
  • Restoration of selected driveway approaches has been tentatively scheduled

E. Washington St, Veterans through Hershey

  • Removal and replacement of the storm sewer inlets has been completed
  • Removal and replacement of the concrete items (sidewalk; ramps) is in progress
  • Removal of the underground utility castings has been completed
  • Removal of the asphalt surface has been completed
  • Installation of the asphalt binder course has been completed
  • Installation of the asphalt surface course has been scheduled for the week of October 27
  • Restoration of selected driveway approaches has been tentatively scheduled

Constitution Trail, Fox Creek bridge over the Interstate to Morris

  • Removal of the asphalt surface has been completed
  • Installation of the asphalt surface course has been completed
  • Removal and replacement of the concrete items (ramps) is in progress

Contact: Katherine Murphy Communications & External Affairs Mgr. Phone: 309-434-2241 Email: [email protected]

Contact: Jim Karch Director of Engineering Phone: 309-434-2980 E-mail: [email protected]

City of Bloomington, IL published this content on October 27, 2025, and is solely responsible for the information contained herein. Distributed via Public Technologies (PUBT), unedited and unaltered, on October 27, 2025 at 15:55 UTC. If you believe the information included in the content is inaccurate or outdated and requires editing or removal, please contact us at [email protected]