News Release - 2026 County Road Project Summary

NEWS RELEASE

June 15, 2026

The Chemung County Department of Public Works (DPW) announces its 2026 County Road Program. The DPW road crews have already started preparing for construction on project roads, including tree trimming and ditch cleaning. Paving and surface treatments will commence in the summer months. Please slow down when approaching and traveling through road work zones.

If you have any questions, please contact the Chemung County Public Works Department at 607-739-3896.

2026 COUNTY ROAD PROJECT SUMMARY

REHABILITATION PROJECTS

COUNTY ROAD

CONSTRUCTION TYPE

BEGIN/END

MILES

CR 64

SPOT BASE REPAIR, TRUE & LEVEL WITH 1.5" HOT MIX ASPHALT OVERLAY

CR64 over NSRR BRIDGE (WEST OF WELLS LANE) TO COMMERCE CENTER RD

2.16

CR 69 - PENNSYLVANIA AVE

2" MILL & FILL WITH HOT MIX ASPHALT

1ST ROUNDABOUT TO ORCHARD PARK RD

1.94

CR 60

1.5" HOT MIX ASPHALT OVERLAY

LOWMAN CROSSOVER TO ROBERTS HOLLOW RD

1.75

CR 50 - WEST DRY BROOK RD

1.5" HOT MIX ASPHALT OVERLAY

DRYBROOK RD TO ROTARY RD

1.60

CR 23 - MALLORY RD

COLD-IN-PLACE RECYCLE WTH 1.5" HOT MIX ASPHALT OVERLAY

WYNCOOP RD TO SOULS HILL RD

1.75

TOTAL

9.20

PRESERVATION PROJECTS

COUNTY ROAD

CONSTRUCTION TYPE

BEGIN/END

MILES

CR 56 - RIVER RD

DOUBLE CHIP SEAL

CR 60 TO DEAD END

1.8

CR 23 - DRYBROOK RD

DOUBLE CHIP SEAL

RIVER RD TO BLACKBURN HILL RD

4.8

CR 21 -WYGANT RD

DOUBLE MICRO PAVE

RAILROAD TRACKS TO OLD ITHACA RD

1.6

TOTAL

8.2

Christopher J. Moss
Chemung County Executive

Chemung County, NY published this content on June 15, 2026, and is solely responsible for the information contained herein. Distributed via Public Technologies (PUBT), unedited and unaltered, on June 27, 2026 at 07:10 UTC. If you believe the information included in the content is inaccurate or outdated and requires editing or removal, please contact us at [email protected]