NEWS RELEASE
June 15, 2026
The Chemung County Department of Public Works (DPW) announces its 2026 County Road Program. The DPW road crews have already started preparing for construction on project roads, including tree trimming and ditch cleaning. Paving and surface treatments will commence in the summer months. Please slow down when approaching and traveling through road work zones.
If you have any questions, please contact the Chemung County Public Works Department at 607-739-3896.
2026 COUNTY ROAD PROJECT SUMMARY
REHABILITATION PROJECTS
|
COUNTY ROAD |
CONSTRUCTION TYPE |
BEGIN/END |
MILES |
|
CR 64 |
SPOT BASE REPAIR, TRUE & LEVEL WITH 1.5" HOT MIX ASPHALT OVERLAY |
CR64 over NSRR BRIDGE (WEST OF WELLS LANE) TO COMMERCE CENTER RD |
2.16 |
|
CR 69 - PENNSYLVANIA AVE |
2" MILL & FILL WITH HOT MIX ASPHALT |
1ST ROUNDABOUT TO ORCHARD PARK RD |
1.94 |
|
CR 60 |
1.5" HOT MIX ASPHALT OVERLAY |
LOWMAN CROSSOVER TO ROBERTS HOLLOW RD |
1.75 |
|
CR 50 - WEST DRY BROOK RD |
1.5" HOT MIX ASPHALT OVERLAY |
DRYBROOK RD TO ROTARY RD |
1.60 |
|
CR 23 - MALLORY RD |
COLD-IN-PLACE RECYCLE WTH 1.5" HOT MIX ASPHALT OVERLAY |
WYNCOOP RD TO SOULS HILL RD |
1.75 |
|
TOTAL |
9.20 |
||
PRESERVATION PROJECTS
|
COUNTY ROAD |
CONSTRUCTION TYPE |
BEGIN/END |
MILES |
|
CR 56 - RIVER RD |
DOUBLE CHIP SEAL |
CR 60 TO DEAD END |
1.8 |
|
CR 23 - DRYBROOK RD |
DOUBLE CHIP SEAL |
RIVER RD TO BLACKBURN HILL RD |
4.8 |
|
CR 21 -WYGANT RD |
DOUBLE MICRO PAVE |
RAILROAD TRACKS TO OLD ITHACA RD |
1.6 |
|
TOTAL |
8.2 |
||
Christopher J. Moss
Chemung County Executive