City of Bloomington, IL

11/23/2026 | Press release | Distributed by Public on 11/23/2026 10:10

Resurfacing Update: November 23, 2026

BLOOMINGTON, IL - The City of Bloomington provides regular updates on resurfacing work throughout the construction season. The most recent update is included below.

For more information on roadwork in the City of Bloomington, visit www.bloomingtonstreets.com, e-mail [email protected] or call 309-434-2980 during regular business hours. Residents can also sign up for e-mail or text updates for Bloomington Streets by visiting www.bloomingtonil.gov/subscribe and subscribing to Bloomington Streets.

FY26 Resurfacing

E. Oakland Ave, west of Prospect through Hershey

  • A final inspection has been completed, and cleanup is in progress

Prospect Rd, Oakland to Empire

  • A final inspection has been completed, and cleanup is in progress

E. Washington St, Veterans through Hershey

  • A final inspection has been completed, and cleanup is in progress

FY27 Resurfacing

Eastland Dr, Fairway to Hershey

  • Installation of the asphalt surface course has been completed
  • Installation of pavement striping has been completed

Four Seasons Rd, north of Oakland through the cul-de-sac

  • Installation of the asphalt surface has been completed
  • Installation of the pavement striping has been completed

St. Joseph Dr, Washington to Eastland

  • Installation of the asphalt surface has been completed
  • Installation of pavement striping has been completed

N. Hershey Rd, north of Lamon through Jumer

Stage 1: Jumer to Rainbow (concrete pavement)

  • Project limit traffic control devices are in place
  • Installation of the asphalt surface course has been completed
  • Installation of the pavement striping has been requested and tentatively scheduled

Stage 2: Rainbow to Lamon (asphalt pavement)

  • The limits and layout of the work zone has been completed
  • Underground utility (JULIE) locations have been requested
  • Resurfacing of this section of Hershey has been rescheduled to Spring 2027

Contact:
Katherine Murphy
Communications & External Affairs Mgr.
Phone: 309-434-2241
Email: [email protected]

Contact:
Jim Karch
Director of Engineering
Phone: 309-434-2980
E-mail: [email protected]

City of Bloomington, IL published this content on November 23, 2026, and is solely responsible for the information contained herein. Distributed via Public Technologies (PUBT), unedited and unaltered, on November 23, 2026 at 16:11 UTC. If you believe the information included in the content is inaccurate or outdated and requires editing or removal, please contact us at [email protected]