10/08/2026 | Press release | Distributed by Public on 10/08/2026 09:34
The Connecticut Department of Transportation (CTDOT) is developing plans under State Project No. 0174-0492 to replace existing traffic control signal equipment in Ansonia, Barkhamsted, Beacon Falls, Canton, Danbury, Sharon, Simsbury, Southbury, Suffield, and Torrington.
The project involves full replacements of the traffic signal equipment at twelve intersections. At applicable locations, pedestrian control features (countdown pedestrian indications, accessible pushbuttons, sidewalk ramps) will be upgraded in an effort to improve accessibility and pedestrian safety.
CTDOT will coordinate with the City/Town during the design phase. The following intersections are included:
Traffic Control Signal - Full Replacement:
The present schedule indicates that the design will be completed in July 2028, with construction anticipated to start in the spring of 2029, assuming acceptance of the project, availability of funding and receipt of any required right-of-way and environmental permits. This project will be undertaken with 20% federal and 80% state funds.
It is CTDOT's policy to keep the public informed and involved when such projects are undertaken. It is important that the community share its concerns with CTDOT to assist in the project's development. If anyone has any questions or comments on this project, contact Kaethe Podgorski, Principal Engineer, at (860) 594-2189 or by e-mail at [email protected]. Please make reference to State Project No. 0174-0492.