DOT - South Dakota Department of Transportation

01/15/2026 | Press release | Distributed by Public on 01/15/2026 14:46

Yankton County Highways Scheduled for Closure for James River Bridge Replacement Project

Yankton County Highways Scheduled for Closure for James River Bridge Replacement Project

For Immediate Release:
Thursday, Jan. 15, 2026

Contact:
Kevin Heiman, PE; Engineering Supervisor, 605-668-2929


MENNO, S.D. - Beginning on Tuesday, Jan. 20, 2026, Yankton County Highway 587 (Stone Church Road) and County Highway 217 (Northwest Jim River Road) will be closed to through traffic for the replacement of the James River Bridge.

The reconstruction project consists of the replacement of the existing bridge and approach grading work. Traffic will be diverted onto the designated detour route at the intersection of 431st Avenue to S.D. Highway 46, S.D. Highway 25, and U.S. Highway 18.

The highway closures will be in effect for the duration of the two-year project. Access to adjacent property will be maintained throughout the project.

The prime contractor for the $7.5 million project is Grangaard Construction of Watertown, SD. The overall project completion date is Nov. 19, 2027.

About SDDOT:
The mission of the South Dakota Department of Transportation is to provide a safe and efficient public transportation system.

For the latest on road and weather conditions, road closures, construction work zones, commercial vehicle restrictions, and traffic incidents, please visit https://sd511.orgor dial 511.

Read more about the innovative work of the SDDOT at
https://dot.sd.gov.

-30-

DOT - South Dakota Department of Transportation published this content on January 15, 2026, and is solely responsible for the information contained herein. Distributed via Public Technologies (PUBT), unedited and unaltered, on January 15, 2026 at 20:46 UTC. If you believe the information included in the content is inaccurate or outdated and requires editing or removal, please contact us at [email protected]