Soluna Finishes Kati 1 and Secures Conditional Base Load Position for All 166 MW in ERCOT
Final 14 MW energized on time, lifting company-wide operating capacity to 206 MW
ALBANY, NY, September 8, 2026 - Soluna Holdings, Inc. ("Soluna" or the "Company") (NASDAQ: SLNH), a developer of green data centers for intensive computing applications, including AI and Bitcoin mining, today announced two milestones at its Project Kati campus in Willacy County, Texas. The Company has energized the final 14 MW at Project Kati 1, completing the 83 MW site, and has been notified that ERCOT has conditionally classified the full 166 MW Kati campus, including the planned Kati 2 AI expansion, as Base Load in its Batch Zero interconnection process.
With Project Kati 1 complete, Soluna's total operating capacity increases to approximately 206 MW, delivering on the timeline the Company outlined on its second-quarter earnings call. Every phase of Project Kati 1 was delivered on time with infrastructure costs on budget.
Batch Zero is ERCOT's transitional process for evaluating large load interconnection requests on a system-wide basis, replacing the prior project-by-project approach. A Base Load classification means a project's interconnection capacity is preserved on the basis of prior study work, and that the project is not subject to further reliability evaluation or megawatt allocation within the Batch Zero study. According to ERCOT, more than 438,000 MW of large load interconnection requests had entered the queue as of mid-2026, with nearly 90 percent coming from data centers.
The classification is conditional pending completion of ERCOT's ongoing verification process, under which ERCOT may remove a project from Batch Zero if the applicant does not respond to its information requests. Soluna is participating in the verification process and expects the full 166 MW to be confirmed as Base Load.
"This is proof that the Soluna model works," said John Belizaire, CEO of Soluna. "We build where the power already is and we bring generation with us, and ERCOT's framework recognizes exactly that. Kati 1 is finished and energized today, and our full 166 megawatts is positioned as Base Load while much of the market is still waiting to learn what it will be allocated."
Project Kati is a 166 MW wind-powered campus in Willacy County, Texas, powered by the Las Majadas wind energy project and built in two phases. Kati 1, the 83 MW first phase, is dedicated to Bitcoin hosting. Kati 2 will add 83 MW for AI and high-performance computing. Built behind the meter, the campus converts stranded renewable energy into productive computing capacity while bypassing the transmission upgrades and interconnection queues that constrain grid-connected development.
Energization of Kati 1 began in February 2026 following ERCOT approval and proceeded in phases. Kati 1A completed its 48 MW on April 1, filled by Galaxy Digital, with the remaining 35 MW energized in phases through the summer. The co-mining agreement with Bitdeer (NASDAQ: BTDR) announced in August is now underway, with equipment being delivered and deployed.
Soluna continues to advance a development pipeline of approximately 6.3 GW, including more than 650 MW of AI and high-performance computing capacity in development at Kati 2 and Project Dorothy 3.
For more information, visit www.solunacomputing.com.