07/01/2026 | News release | Distributed by Public on 07/01/2026 11:12
Staff at the Nuclear Regulatory Commission have recommended the agency issue a construction permit to the Tennessee Valley Authority for its plans to construct a GE Vernova Hitachi Nuclear Energy (GVH) BWRX-300 reactor at the Clinch River site in Tennessee, according to the safety evaluation report published as part of the construction permit application process.
The recommendation to the commissioners is a boon for the project, which proposes constructing a 300-MWe boiling water reactor in Oak Ridge, Tenn. The June report-available in the NRC ADAMS library-presents the NRC staff's review of TVA's 2025 application and any additional information staff received through April of this year.
The findings: According to NRC staff, the application met five key criteria:
The Advisory Committee on Reactor Safeguards (ACRS) met in early June to complete its review of the safety aspects of the TVA application. Its conclusions and recommendations-published separately from the larger safety evaluation report-include the following:
The report stated that the safety strategy used by GVH must demonstrate "timely reconciliation" with 10 CFR Part 50 to support the application's safety case. ACRS advised NRC staff to "capture lessons learned from this review for efficiently reconciling such defense-line type approaches with prescriptive light water reactor regulatory requirements for future applications."
ACRS did provide some "important concerns" that needed to be addressed at the operating license stage and at the initial startup. According to the report, this included "operational testing to confirm natural circulation stability especially at startup and low power, confirmation of isolation condenser system (ICS) performance and associated control and interlock functions, and design extension conditions and practical elimination claims (beyond design basis events)."
Ahead of schedule: The publishing of the safety evaluation report outpaced the original timeline, according to a letter NRC staff sent to TVA regarding the review status of the construction permit application. The agency originally informed TVA that the evaluation report would be complete by November. The expedited timeline is a result of "review efficiencies and frequent and productive engagements with TVA," according to the letter.
This has resulted in NRC staff projecting it will need about 16,500 staff hours to complete the review and issuance of the permit, a reduction from the estimate of 25,000 staff hours reported to TVA last year. The estimate of contractor costs to complete the review and issuance is approximately $1.4 million, which has not changed since last year, according to the letter.